Weil-McLain 550-141-826/1201 manual Check-Out Procedure, Check off steps as completed

Page 24

Check-Out Procedure

Check off steps as completed:

1. Boiler and heat distribution units filled with water?

2. Automatic air vent, if used, opened one full turn?

3. Air purged from system? Piping checked for leaks?

4. Air purged from oil piping? Piping checked for leaks?

5. Flue cap in place and tightened? Burner door closed, sealed and nut tight? Burner plugged in and service switch on?

Obtain gas-tight seal to prevent possible flue gas

leakage and carbon monoxide emissions, leading to severe personal injury or death.

6. Proper draft and burner flame? Final adjustment made with combustion test equipment?

7. Test limit control: While burner is operating, move indicator on limit control below actual boiler water temperature. Burner should go off while circulator continues to operate. Raise setting on limit control above water temperature and burner should re-ignite.

8. Test additional field-installed controls: If boiler has a low water cutoff, additional high limit or other controls, test for operation as outlined by manufacturer. Burner should be operating and should go off when controls are tested. When controls are restored, burner should re-ignite.

9. Limit control set to system temperature requirements (max. 220°F)?

10. For multiple zones, flow adjusted to distribute heat in all zones?

11. Thermostat heat anticipator setting (if available) set properly? Refer to “Connect wiring,” page 19.

12. Boiler cycled with thermostat? Raise to highest setting and verify boiler goes through normal start-up cycle. Lower to lowest setting and verify boiler goes off.

13. Observed several operating cycles for proper operation?

14. Set room thermostat(s) to desired

room temperature?

15. Completed Installation and Service Certificate below?

16. Reviewed Maintenance and Service Manual with owner or maintenance person and instructed person to keep for future reference?

17. Returned all instructions provided with boiler to its envelope and placed with boiler for future reference?

Installation and Service Certificate

Date Installed: ______________________________________________

Boiler Model Number: __________________Series: _________

CP Number(s):______________________________________________

Installation instructions have been followed.

Check-out procedure has been performed.

Above information is certified to be correct.

Measured Btu or GPH Input: _____________________________

Information received and left with owner/

 

maintenance person.

 

Installer:__________________________________________________________________________________________________________________________

(Company)

(Address)

(Phone)

 

_________________________________________________________________

24

(Installer’s Signature)

 

Image 24
Contents This Manual Includes Installation Start-Up Boiler Parts Symbol Definitions When Calling or Writing About the BoilerRead This Page First Hazard DefinitionsTable of Contents Before Installing Boiler Installations must comply withBefore selecting boiler location Provide clearances around boiler see FigureProvide air for combustion and ventilation Lay a foundation, if neededBoiler Foundation Size Table Install Packaged Boiler Place boilerPerform hydrostatic pressure test Go to page 12 to connect breeching and ventingChange From Back Flue Outlet to Top Flue Outlet Optional Install Non-Packaged Boiler Fiberglass wool and ceramic fiber materialsFlue Collector Hood Install Packaged and Non-Packaged Boiler Install jacket sizes 7 through 9 onlyInstall boiler controls Control Tapping TableInstall burner also refer to instructions packed with burner Connect Breeching General chimney requirementsMinimum Chimney Size Table Connect Breeching Install piping Connect Water PipingGeneral piping information Diaphragm expansion tank FigureIsolation Piping Multiple Zones Zoning with circulatorsPiping for systems requiring temperatures below 140F Use with refrigeration systems Connect Wiring General wiring requirementsThermostat wiring Burner wiringConnect Wiring Connect Wiring Connect Oil Piping General oil piping requirementsOil piping connection at burner Start-Up Fill the systemTips for water systems To place in operationCheck-Out Procedure Check off steps as completedBurner adjustments for P and a boilers AppendixClose clearance installation Dimension a Parts List DescriptionParts Drawing Dimensions DimensionsIntermediate DIA Ratings WGO Gold OIL Water Boiler Ratings

550-141-826/1201 specifications

The Weil-McLain 550-141-826/1201 is a high-efficiency boiler designed for commercial applications, providing unmatched performance, reliability, and advanced technology features. This model is specifically engineered to cater to a range of heating needs, making it suitable for various settings, such as schools, hospitals, and large commercial spaces.

One of the key features of the Weil-McLain 550-141-826/1201 is its impressive thermal efficiency. With a high AFUE (Annual Fuel Utilization Efficiency) rating, this boiler maximizes energy usage, resulting in lower utility costs for end-users. The efficient performance not only translates to better energy savings but also contributes to a reduced carbon footprint, aligning with modern sustainability goals.

The powerful burner technology incorporated in the Weil-McLain 550-141-826/1201 ensures precise control over the combustion process. This results in consistent heating performance and minimizes emissions, meeting stringent environmental regulations. The unit utilizes advanced modulation technology, which allows the burner to adjust its output according to the demand, providing significant energy savings and enhanced comfort.

Another standout characteristic of this boiler is its robust construction. Built with high-quality materials, the Weil-McLain 550-141-826/1201 is designed to endure demanding conditions, ensuring longevity and reduced maintenance needs. The boiler features a durable heat exchanger, which optimizes thermal transfer efficiency while resisting corrosion and thermal stress.

The user-friendly controls and monitoring systems enhance the operational experience, allowing for easy adjustments and status checks. The integrated diagnostic capabilities provide valuable insights for troubleshooting, making maintenance straightforward and reducing downtime.

Furthermore, the versatility of the Weil-McLain 550-141-826/1201 allows for multiple installation configurations, accommodating different system requirements and space limitations. Its compact design makes it an ideal choice for facilities where space is a premium.

In summary, the Weil-McLain 550-141-826/1201 stands out in the commercial boiler market with its high efficiency, innovative burner technology, robust construction, user-friendly controls, and versatile installation options. This model exemplifies Weil-McLain's commitment to energy-efficient heating solutions, setting a benchmark for performance and reliability in the industry.