DESIGN GUIDELINES FOR OUTSIDE COMBUSTION AIR CONNECTION

1)For installations with horizontal through-the-wall exhaust, it is strongly recommended that the stove combustion air be connected to the outside. If the home is newer or has been tightly insulated it is required to install outside combustion air. If you do not, then bring a 4-6 inch intake into the furnace room in the basement.

2)Connection to outside the house is REQUIRED for mobile home installations.

90 DEGREE BEND TERMINATION

WIND HOOD TERMINATION

Wind Hood

3” Min. Diameter

3”

2”

6”

3)Only noncombustible pipe 3 inches in diameter is approved to use for outside air connections (straight or flexible). PVC pipe is NOT approved and should NEVER be used.

4)If the air inlet is connected to the outside, it MUST be terminated with a vertical 90-degree bend (down) or with a wind hood. Failure to do so could result in a burn back during high winds blowing directly up the air inlet during a simulta- neous power failure (see diagram above).

5)Blockage, excessive length, or bends in the air intake pipe will starve the stove of combustion air. A 90-degree bend is equivalent in restriction to approximately 30 inches of straight inlet pipe.

CAUTION: The operation of exhaust fans such as bath room fans, attic fans, etc. might starve the heater of combustible air creating a negative pressure in the room. Provide adequate ventilation in the room accompanying the heater.

8

USSC

Image 8
Contents 6033 Specifications CongratulationsSafety Steps Burning Solid FuelsBurning Solid Fuels Installation Requirements Clearances to CombustiblesClearances to Combustibles Guidelines for Exhaust Venting Systems DesignGuidelines for Exhaust Venting Systems Design Design Guidelines for Outside Combustion AIR Connection Installation Configurations Mobile Home Installation RequirementsAlcove Installation Requirements ALCOVE-THROUGH the Wall Installation RequirementsCorner Installation Outside Wall TerminationFreestanding Stove Installation Requirements Horizontal Exhaust TerminationInside Vertical Pipe with Roof Termination Ussc Removal of Broken or Damaged Ceramic Glass Glass MAINTENANCE, Removal and ReplacementCleaning the Glass Stove Controls Lighting Instructions Damper Control FunctionDisposal of Ashes Disposal of AshesCircuit Board Functions Soot and Flyash Formation and Need for Removal Setting the DraftMaintenance Instructions Maintenance Instructions Spring CleaningRear View Side View Automatic Safety FeaturesHopper Auger Safety Switch Location Thermostat Installation Fuel AdditiveTrouble Shooting Unplug stove before preforming any maintenance workTrouble Shooting Opening with latex or an inexpensive Wiring Diagram Repair Repair Parts LIST-6033 HOW to Order Repair Parts