If the area above the ceiling is NOT an attic, position and secure the ceiling firestop on the ceiling side of the previously cut and framed hole.

JOIST

CEILING

NAILS (4 REQUIRED)

CEILING FIRESTOP

Figure 26. Ceiling Firestop (Ceiling Side)

If the area above the ceiling IS an attic, position and secure the firestop on top of the previously framed hole.

NOTE: Keep insulation away from the vent pipe at least 1 inch (25mm).

NOTE: There must be NO INSULATION or other combustibles inside the framed firestop opening.

 

NAILS (4 REQUIRED)

 

RAFTER

CEILING

 

 

CEILING FIRESTOP

Figure 27.

Attic Firestop

C. Vent Termination

For Horizontal Terminations - To attach and secure the termination to the last section of horizontal vent refer to the Cinch Pipe and Termination Cap installation instructions.

Push on and snap lock as described at the beginning of the Installing Vent Components section.

The termination kit should pass through the wall firestops from the exterior of the building.

Adjust the termination cap to its final exterior position on the building and interlock the flue sections.

WARNING: THE TERMINATION CAP MUST BE

!POSITIONED SO THAT THE ARROW IS POINTING UP.

For trapezoidal cap termination kits:

Using screws secure the cap to the exterior wall through the flanges in the cap.

!WARNING: VENTING TERMINALS SHALL NOT BE RECESSED INTO A WALL OR SID-

ING. VENT TERMINATION CLEARANCES MUST BE FOLLOWED TO AVOID FIRE DANGER. SEE VENT TERMINATION MINIMUM CLEARANCES DI- AGRAM ON FOLLOWING PAGE.

7 1/4" (184mm)

Figure 28. Trapezoid Termination Cap

Heat & Glo • PIER-HVB-IPI, ST-HVB-IPI2006-901 Rev. C • 12/07

27

Image 27 Contents
ST-HVB-IPI Safety and Warning Information Table of Contents Pier-HVB-IPI Log AssemblyPIER-HVB-IPI Service Part ListST-HVB-IPI ST-HVB-IPI PIER-HVB-IPI, ST-HVB-IPI IPI Valve AssemblyInstallation Codes High Altitude Installations Appliance CertificationCertification Requirements for the Commonwealth of Massachusetts Vent Directly BELOW. Keep Clear of ALL OB- StructionsManufacturer Requirements Pre-install Preparation Introducing the Heat & Glo Gas FireplacesANY Such Action MAY Possibly Cause a Fire Hazard Diagram of the PIER-HVB-IPI Diagram of the ST-HVB-IPI Fireplace Dimensions and Locations Locating the FireplaceClearance Requirements 787 Framing the FireplaceModel AT Each Joint Identifying Vent Components Installing the Vent SystemVent System Approvals Tems or Components MAY be UsedMax. Run Straight UP Vertical VentingMAX .2 M Straight OUTVenting with One 90 Elbow Venting with Two 90 Elbows + H1 FT Venting with three 90 elbows + V1 FT + H1 FT Attach the First Vent Component to the Starting Collars Installing Vent ComponentsContinue Adding Vent Components Install Support BracketsPositioned SO That the Arrow is Pointing UP Attic FirestopVent Termination Minimum Clearances Minimum Height from Roof to Lowest Discharge Opening Fireplace Junction BOX in a IPI System Positioning, Leveling, and Securing the FireplaceGas Control System Securing of a FireplaceGas Pressure Requirements Gas Supply LineWiring the Fireplace For Intermittent Pilot Ignition Wiring Operation using Battery PowerAppliance Requirements Fan Installation Optional Accessories Wall SwitchUse to manually control fan with wall switch Wall Switch Installation for Fan OptionalFinishing ANY MannerHearth Extensions Glass Specifications Model Type Installing Trim, Logs & Ember MaterialInstalling the Trim Shutter SettingsPlacing the Ember Material Using a 5/16 nut driver remove the two bolts see FigureLighting the Fireplace After the InstallationDouble-check for faulty components Before Lighting the FireplaceImportant Turn OFF the GAS Before Servicing Your Fireplace Fireplace MaintenanceContact Information