State Industries GP6 50 Sequence of INSTALLATIONS, Figure, Vent Termination Figure

Page 22

may be easier to mark both the inside and outside wall. Align holes by drilling a hole through center of the template from the inside through to the outside. The template can now be positioned on the outside wall using the drilled hole as a centering point for the template.

3.A) MASONRY SIDE WALLS

Chisel an opening approximately one half inch (1.3 cm) larger than the marked circle.

B) WOODEN SIDE WALLS

Drill a pilot hole approximately one quarter inch (0.64 cm) outside

of the marked circle. This pilot hole is used as a starting point for a saws-all or sabre saw blade. Cut around the marked circle

staying approximately one quarter inch (0.64 cm) outside of the line. (This will allow the vent to easily slide through the opening.

The resulting gap will be covered up by the Vent Terminal cover

plate.) Repeat this step on inside wall if necessary.

bead of caulking (not supplied) around the gap between the pipe and cover plate. Apply enough to fill some of the gap between the pipe and wall. Place some of the caulking on the back of the plate to hold it against the wall after installation. If the vent pipe is installed up to the wall, with a coupling on the end against the wall opening, the pipe with the vent terminal can be prepared for gluing before inserting through the wall. Slide the pipe through the wall and insert into the coupling on the other side of the wall, making sure that the vent terminal ends up pointed in the correct position, see Figure 18.

SEQUENCE OF INSTALLATIONS, FIGURE 18

Cut a length of PVC pipe about 3.5 inches (8.9 cm) longer than wall

 

thickness at the opening. Glue vent terminal to this section of pipe. Slide

VENT TERMINATION - FIGURE 18.

the wall plate over the pipe to stop against the vent terminal. Place a

CAUTION

LABEL ALL WIRES PRIOR TO DISCONNECTION WHEN SERVICING CONTROLS. WIRING ERRORS CAN CAUSE IMPROPER AND DANGEROUS OPERATION. VERIFY PROPER OPERATION AFTER SERVICING.

POWER VENT WIRING SCHEMATIC - FIGURE 19.

22

Image 22
Contents Printed Whenever maintenance adjustment or service is required197425-005 Approvals Safe INSTALLATION, USE and ServiceImportant Definitions General Safety Information General Safety Information Table of Contents IntroductionSignage Installation of Carbon Monoxide DetectorsApproved Carbon Monoxide Detectors ExemptionsReplacement Parts and Deliming Products Typical InstallationElbow Access Door Condensate Hose and Drain PAN Mixing Valves Less Severe Burns 2nd & 3rd DegreeLocating the NEW Water Heater Facts to Consider About the LocationInsulation Blankets Air REQUIREMENTsFresh Air Openings For Confined Spaces Unconfined SpaceConfined Space Outdoor Air Through Two OpeningsOutdoor AIR Through TWO Vertical Ducts Outdoor AIR Through TWO Horizontal DuctsAIR from Other Indoor Spaces Water Piping Installing the NEW Water HeaterChemical Vapor Corrosion Space Heating and Potable Water SystemThermal Expansion Temperature-Pressure Relief ValveValve and Pipe Insulation High Altitude Installation Gas PipingSediment Traps Filling the Water HeaterVent Pipe Assembly VentingTermination Clearances Sidewall Power Vent Vent Pipe TerminationCondensate Planning the Vent SystemBreathing Hazard Carbon Monoxide Gas Installation of Vent System Blower Assembly InstallationVent Terminal INSTALLATION, Sidewall Power Vent Wiring Schematic Figure Sequence of INSTALLATIONS, FigureVent Termination Figure Installation of Vent SYSTEM, Sidewall Installation of Vertical Vent SystemVent Attenuation Assembly Installation Vertical VAA Installations RecommendedInch vent Vertical VAA Installations Vent Pipe Preparation Recommended BRUSH* Size for Primer Cement ApplicationsStep F Step BStep E Step GPage Temperature Regulation GAS Control Valve Front ViewStart UP Conditions Periodic MaintenanceFor Your Information Operational ConditionsHousekeeping Burner CleaningBurner Operation and Inspection Anode ROD InspectionTo Drain the Water Heater Storage Tank Temperature-Pressure Relief Valve TestDraining and Flushing To Flush the Water Heater Storage TankService Leakage CheckpointsRepair Parts List Trouble Shooting Troubleshooting GuidelinesLED Status Problem Solution LED Status Problem Solution Troubleshooting Guidelines Page CondItIons and eXceptIons ServIce and laBor responsIBIlItYClaIM procedure LIMItatIon on IMplIed warrantIesCopyright 2010 State Industries, Inc. All rights reserved