State Industries GP6 50 instruction manual Installation of Vent SYSTEM, Sidewall

Page 23

INSTALLATION OF VENT SYSTEM, SIDEWALL

With the route of the venting system and selection of materials completed, as discussed in the section of this manual titled PLANNING THE VENT

SYSTEM, the through the wall vent terminal in place and the first section of piping, up to first elbow, installed at the blower it is time to complete the

installation of the venting system for the sidewall installation.

GRADE

SNORKEL

*MIN. 12” (30 cm)

ABOVE GRADE OR

*MIN. 12” (30 cm)

ABOVE

ANTICIPATED

SNOW LEVEL

INSTALL A SNORKEL AS SHOWN

HERE ONLY IF NECESSARY TO

ACHIEVE THE 12” MINIMUM

CLEARANCE ABOVE

THE HIGHEST ANTICIPATED

SNOW LEVEL.

FIGURE 20

It is recommended that the completion of the venting system start at the blower assembly and run to the coupling on the inside wall of the vent terminal, Figure18.

The vent system piping should be supported every 5 feet (1.5 m) of vertical run and every 3 feet (91 cm) of horizontal run. Follow vent pipe manufacturer’s instructions for proper joining procedures.

If necessary to achieve the 12” minimum clearance above the highest anticipated snow level, install a snorkel as shown in bottom portion of Figure 20.

NOTE: With the installation of a snorkel it is necessary to use two 90° elbows that shall be considered along with the

additional vent pipe when calculating maximum equivalent feet of venting.

INSTALLATION OF VERTICAL VENT SYSTEM

A proper flashing or “BOOT” should be used to seal the pipe

where it exits the roof. The total vent system should not exceed the equivalent feet of pipe as listed in Table 1.

Provide support for all pipe protruding through the roof. All piping should be properly secured. The vent system piping should be supported

every 5 feet (1.5 m) of vertical run and every 3 feet (91 cm) of horizontal run. Follow vent pipe manufacturer’s instructions for proper

joining procedures.

FIGURE 21

IMPORTANT

The vent system must terminate so that proper clearances are maintained as cited in local codes or the current edition

of the National Fuel Gas Code (ANSI Z223.1) or the Natural Gas and Propane Installation Code (CAN/CSA-B149.1) and as

listed below:

1.Vent Termination must extend a minimum of 12 inches (30 cm) above roof or 12 inches (30 cm) above the anticipated snow level to prevent blockage of the vent termination, as shown in Figures 20 and 21.

23

Image 23
Contents 197425-005 Whenever maintenance adjustment or service is requiredPrinted Important Definitions Safe INSTALLATION, USE and ServiceApprovals General Safety Information General Safety Information Introduction Table of ContentsExemptions Installation of Carbon Monoxide DetectorsApproved Carbon Monoxide Detectors SignageElbow Access Door Typical InstallationReplacement Parts and Deliming Products Condensate Hose and Drain PAN Less Severe Burns 2nd & 3rd Degree Mixing ValvesFacts to Consider About the Location Locating the NEW Water HeaterAir REQUIREMENTs Insulation BlanketsOutdoor Air Through Two Openings Unconfined SpaceConfined Space Fresh Air Openings For Confined SpacesAIR from Other Indoor Spaces Outdoor AIR Through TWO Horizontal DuctsOutdoor AIR Through TWO Vertical Ducts Space Heating and Potable Water System Installing the NEW Water HeaterChemical Vapor Corrosion Water PipingValve and Pipe Insulation Temperature-Pressure Relief ValveThermal Expansion Gas Piping High Altitude InstallationFilling the Water Heater Sediment TrapsVenting Vent Pipe AssemblyVent Pipe Termination Termination Clearances Sidewall Power Vent Breathing Hazard Carbon Monoxide Gas Planning the Vent System Condensate Vent Terminal INSTALLATION, Sidewall Blower Assembly InstallationInstallation of Vent System Vent Termination Figure Sequence of INSTALLATIONS, FigurePower Vent Wiring Schematic Figure Installation of Vertical Vent System Installation of Vent SYSTEM, SidewallVertical VAA Installations Recommended Vent Attenuation Assembly InstallationInch vent Vertical VAA Installations Recommended BRUSH* Size for Primer Cement Applications Vent Pipe PreparationStep G Step BStep E Step FPage GAS Control Valve Front View Temperature RegulationOperational Conditions Periodic MaintenanceFor Your Information Start UP ConditionsAnode ROD Inspection Burner CleaningBurner Operation and Inspection HousekeepingTo Flush the Water Heater Storage Tank Temperature-Pressure Relief Valve TestDraining and Flushing To Drain the Water Heater Storage TankLeakage Checkpoints ServiceRepair Parts List LED Status Problem Solution Troubleshooting GuidelinesTrouble Shooting LED Status Problem Solution Troubleshooting Guidelines Page LIMItatIon on IMplIed warrantIes ServIce and laBor responsIBIlItYClaIM procedure CondItIons and eXceptIonsCopyright 2010 State Industries, Inc. All rights reserved