Enviro C-10914 owner manual Do not interfere with the structural integrity of the walls

Page 19

Initial Installation

QUALIFIED INSTALLERS ONLY

NOTES:

(1)The four (4) wood screws provided should be replaced with the appropriate fasteners for stucco, brick, concrete, or other types of siding.

(2)For buildings with vinyl siding, a vinyl siding standoff, should be installed between the vent cap and the exterior wall (see Figure 19). Attach the vinyl siding standoff to the horizontal termination. The vinyl siding standoff prevents excessive heat from possibly melting the vinyl siding material. Note that the horizontal vent termination bolts onto the flat portion of the vinyl siding standoff (shaded area in Figure 20), so that an air space will exist between the wall and the vent termination.

NOTES:

(1)The horizontal run of vent pipe must be level and of run towards the termination. Never allow temperature and may present the possibility of a

should have a 1⁄4 inch rise for every one foot the vent to run downward. This could cause high fire.

(2)The location of the horizontal vent termination on the exterior wall must not be easily blocked or

obstructed. Refer to INITIAL INSTALLATION - VENT CONFIGURATIONS AND RESTRICTOR SETTINGS.

(3)When installing a vent pipe in a chase the minimum clearance to combustibles is 2” (51 mm).

(4)Maintain manufacturer’s clearances to combustibles with venting.

CORNER INSTALLATIONS:

Do not interfere with the structural integrity of the walls.

When rear venting if a 90° bend is used the maximum horizontal vent that can be used is 6” (152mm) and if a 45° bend is used the maximum horizontal vent that can be used is 12” (305mm). For installations with a 36” (915 mm) snorkel refer to Figure 21 and ‘Initial Installation - Installation of Rear Vented’.

For other corner installations refer to Figure 22 and INITIAL INSTALLATION - VENT CONFIGURATIONS AND RESTRICTOR

SETTINGS.

 

 

 

Figure 21: Corner installation rear vented with

 

Figure 22: Corner installation top vented.

snorkel.

 

 

19

Image 19 Contents
Westport For Your SafetyGeneral Safety PrecautionsTable of Contents TOP Vent DV Codes And ApprovalsRear Vent DV Dimensions SpecificationsOperating Instructions For Your Safetyread Before OperatingGas valve Electronic Ignition Module Location Maintenance And ServiceHandles for Removing Door To ReplaceStep To be Installed by a Qualified Service Agency onlyConversion instructions Natural Gas Qualified Installers only Initial InstallationManufacturer Trade Name Nominal Sizes Are Permitted to Reach the Outside Vent Termination Run Common Horizontal Installation Pipes and fittings, are Installing Vent Cap with Vinyl Siding Stand Off Do not interfere with the structural integrity of the walls Wall Framing for Hole for Vertical OnceRoof Pitch Minimum Height Feet Meters Multi-Story Vent Pipe Installation KIT Components Installation InstructionsCut away of spacers on Flex Pipe Fire stop Assembly of Venting into a Class ‘A’ Chimney Screws removed in see Figure Turn the elbow to the rear vent position and re-fasten withInstallation for Top Vented Horizontal Termination Corner InstallationWiring Diagram InstallationVenting of a Fireplace Fitted with the Drafthood Adaptor Canadian InstallationsA. Installations General Venting InformationSpill Switch Replacement Automatic Safety Shut DownOptional Finishing To Test Valve Pressures GAS Line ConnectionWiring Diagram For Fan Control Wire Size Max. LengthOptional Blower Fan Installation Secondary InstallationComplete Log Placement Log Placement with Rock Wool Brick panel bracket, slots shown Problem Possible Cause Solution Trouble ShootingReference Number Part Description Part Number Parts List CastCast Leg Each Painted Parts Diagram Cast Reference Part Description Part Number Parts List ComponentsParts List Components Parts Diagram Components To the Dealer WarrantyInstallation Data Sheet