SERVICE (cont.)

CONTROL THERMOSTAT - FMD-1 & FMD-2 (cont.)

a)120 volts ac for two wire 120 volt models.

b)208 volts ac for three wire 120/208 volt models.

c)240 volts ac for three wire 120/240 volt models.

5.Disconnect the dispenser from the power source.

If voltage is present as described the control thermo- stat is operating properly. Reinstall bulb into the tank. If voltage is not present as described, replace the thermostat.

Removal and Replacement.

1.Remove the thermostat capillary bulb by firmly pulling-up on the capillary at the tank lid. This will disengage the grommet from the tank lid.

2.Loosen the two #6-32 screws securing the ther- mostat to the front tank mounting bracket.

3.Disconnect the wires from the thermostat.

4.Remove thermostat and remove the screws and spacers from the thermostat.

5.Discard thermostat.

6.Install two spacers and two #6-32 screws on the new thermostat.

7.Position the thermostat on the botttom side of the front tank mounting bracket and tighten the two #6-32 screws.

8.Slide the grommet to the line 4.5" above the bulb on the new capillary tube.

9.Insert the capillary bulb through the hole in the tank lid and press the grommet firmly and evenly so that the groove in the grommet fits into the tank lid.

10.Carefully bend the capillary tube so that the tube and bulb inside the tank are in the vertical position and away from any electrical connections.

11.Refer to Fig. 11 and reconnect the wires.

NOTE - The capillary tube must be clear of any electri- cal termination and not kinked.

BLK from Limit

Thermostat

BLK from Tank

Heater Switch

 

P1668

FIG. 11 THERMOSTAT TERMINALS

 

CONTROL BOARD - FMD-2 ONLY

J1

 

J2

 

J4

 

J3

 

FIG. 12 CONTROL BOARD

P1666

 

Location:

The Control Board is located behind the lower front access cover mounted on the component bracket.

Test Procedure:

Liquid Level Control Circuitry:

1.Disconnect the dispenser from the power source.

2.Disconnect the six pin connector from J3 of the control board.

3.Check the voltage across pins 5 & 6 of the six pin connector on the wiring harness with a voltmeter. Connect the dispenser to the power source. The indication must be 24 volts ac.

4.Disconnect the dispenser from the power source.

If voltage is present as described, proceed to step 5. If voltage is not present as described, refer to the wiring diagram and check the dispenser wiring har- ness.

5.Reconnect the six pin connector of the wiring harness to J3 of the control board.

20

29112 101598

 

Image 20
Contents FMD-1 FMD-2 Warranty IntroductionUser Notices FMD-1 FMD-228368.0001 00656.0000FMD-1 only Initial SET-UP Electrical RequirementsElectrical HOOK-UP Plumbing RequirementsRinse Timer FMD-2 only Initial Fill & HeatLiquid Level Control Running a Rinse SequenceCleaning AdjustmentsHopper Motor Speed Adjustment FMD-1 Cold Beverage SET-UP Optional FMD-2 onlyHopper Motor Speed Programing FMD-2 Draining the HOT Water TankTroubleshooting ProblemProduct will not dispense Probable CauseProbable Cause Remedy Problem Probable Cause Problem Probable Cause Remedy Refer to Service Lamp, see page 29 for lamp replacement Dispenser is making unusualService Component AccessContents Auger Drive Components FMD-1Retainer Clip Hopper Assembly Hopper LidSpacer Auger Motor Hopper Base Dust Seal Washer Retainer Clip Ing panelAuger Drive Components FMD-2 Auger Drive Components FMD-1To the rear of the auger motor mounting panel Hopper Hopper Assy Hopper Dust Seal Auger Drive Components FMD-2Bushing Panel Auger Drive Shaft Remove auger motor and discard Disconnect the wires from the auger motor 16 to be removedRemove dust seal 17 from auger motor Ballast FMD-1 & FMD-2 LocationControl Board FMD-2 only Thermostat TerminalsService Dispense Switch Dispense Switchs FMD-1 & FMD-2 Dispense Switch Terminals P1449 FAN FMD-1 & FMD-2FMD-2 Frother and Whipper Motor FMD-1 shown & FMD-2 Whipper Motor Terminals P1221Hopper Drive Board FMD-1 only Hopper Drive BoardHopper Drive Board FMD-1 only Hopper Drive Board TerminalsLamp Replacement Refer to Fig Door Assy Upper Panel Lamp Holders Lower PanelLamp Replacement Refer to As assemblyLamp Starter and Socket Refer to Location Level Control Board and Level Probe FMD-1 onlyReconnect the violet wire to terminal Level Control Board and Level Probe FMD-1 onlyRINSE/RUN Switch FMD-1 LocationBLK from Main Harness WHI/BRN to YEL to Control Board J2-3 RINSE/RUN Switch FMD-2WHI/RED to Solenoid Valve Cold Water OPTIONALFMD-2 only Cold Water Solenoid ValveFMD-1 Solenoid Valve Dispense FMD-1 & FMD-2 Solenoid Valve Inlet FMD-1 & FMD-2 Tank HeaterMain Harness Thermostat Tank Heater Switch FMD-1 shown & FMD-2Tank Heater FMD-1 shown & FMD-2 Transformer FMD-2 only WHI/GRN T7 WHI/BLK T12Schematic Wiring Diagram FMD-1 BLU WHISchematic Wiring Diagram FMD-2

FMD-1 FMD-2 specifications

The Bunn FMD-1 and FMD-2 models represent a significant advancement in the realm of coffee brewing equipment, catering to the demands of both commercial establishments and serious coffee enthusiasts. These machines are designed to efficiently brew high-quality coffee while minimizing operational complexity.

The Bunn FMD-1 is a single brewer, while the FMD-2 features dual brewing capabilities. This distinction allows the FMD-2 to meet higher coffee volume demands, making it an ideal choice for bustling cafes or restaurants where efficiency is paramount. Both models are engineered with a robust stainless steel construction, ensuring durability and longevity in high-traffic environments.

One standout feature of both models is the infusion technology. This proprietary system enhances the extraction process, allowing for optimal flavor development. The machines utilize a programmable brewing timeline, which provides users with a high level of control over the brewing variables such as time and temperature. This leads to a customizable brewing experience tailored to specific coffee blends or personal taste preferences.

Additionally, these brewers are equipped with an integrated hot water faucet, offering convenience for making tea, hot chocolate, or even instant soup. This multifunctionality improves workflow in busy kitchens, as it eliminates the need for separate hot water dispensers.

The FMD series is also designed with user-friendly interfaces. The digital display provides clear, intuitive information about the brewing process, including brew progress and maintenance alerts. This makes it easy for operators to monitor and manage the machine, ensuring consistency and quality in every cup.

Moreover, both models are designed for quick and efficient cleaning. The removable brewing components facilitate maintenance, which is crucial in a commercial setting where hygiene and equipment uptime are critical.

In terms of capacity, the FMD-1 brews up to 3.8 gallons per hour, while the FMD-2 can produce an impressive 7.5 gallons per hour, demonstrating their suitability for high-volume service.

Overall, the Bunn FMD-1 and FMD-2 models embody the perfect blend of technology, efficiency, and user-centric design, making them a valuable addition to any coffee service operation. Their ability to deliver consistent, high-quality coffee with ease is sure to enhance the customer experience and streamline operations simultaneously.