GE JVB34, JVB64, JVB35 Install the Downdraft, Install the Ductwork, Install the Electrical Wiring

Page 10

INSTALLATION INSTRUCTIONS

(continued)

Install the Downdraft

Mounting screws

Leveling bracket– flange facing out

Leveling bracket– flange facing in

1.Set the downdraft into the opening. Extend the leveling brackets to the floor of the cabinet so the downdraft sits straight. (NOTE: Leveling brackets can be removed and re-attached in other positions. The bottom flange may have to face inward in tight cabinet installations.)

2.Secure the downdraft to the countertop

as follows: Hold the downdraft against the back of the countertop cut-out and tighten the 2 mounting screws (one on each end of unit) on the underside of the countertop. Use a wood shim between the screw and the underside of granite countertops.

3.Screw the leveling brackets to the bottom of the cabinet. Tighten the screws holding the leveling bracket to the unit on each side.

Install the Ductwork

CAUTION- BEFORE CUTTING A HOLE IN CABINET FOR DUCTWORK: Check for interference with floor joists, wall studs, electrical wiring or plumbing.

31⁄4x 10to 6RD. Transition

Blower

Collar

Screws6RD. Elbow &

ductwork

1.Cut the hole in the cabinet as well as holes in the wall or floor as necessary.

2.Mount the roof or wall cap and work back towards the cabinet, attaching all ductwork, elbows and transitions as previously planned. Tape all ductwork connections to make them secure and air tight.

3.Connect the ductwork (and transition,

if required) to the downdraft. If necessary, LOOSEN wing nuts and screws that hold the blower in place, and slide the blower left or right to meet the ductwork. Re-tighten the screws and wing nuts.

NOTE: A 314″ x 10″ collar is provided for installers who prefer to rivet the cutwork to the unit. This will allow the blower to be removed and replaced easily in service situations without disturbing the ductwork.

Install the Electrical Wiring

1.Mount a standard wiring box, with

3-pronged outlet, inside the cabinet. Make sure the downdraft’s power cord can easily reach it.

2.Run the appropriate power cable into the cabinet and connect it to the outlet.

3.Plug the downdraft’s power cord into the outlet.

10

Image 10
Contents Consumer Services Care and CleaningOperating Instructions, Tips Installation Instructions for General Electric Hood Important Safety InstructionsIf You Need Service Cooking Tips Using Your Downdraft Vent SystemServicing ControlsCare and Cleaning QUESTIONS? USE this Problem SolverSpecifications Installation InstructionsRequirements for an approved installation Take Measurements30″ COOKTOPS/DOWNDRAFT Units JVB34, JVB35, JVB9336″ COOKTOPS/DOWNDRAFT Units JVB64, JVB65, JVB96Plan the Ductwork Steps to Determine Flexible Ducting’s Equivalent LengthChanging Blower Discharge Optional Plan the WiringPreparation Down DischargeInstall the Ductwork Install the DowndraftInstall the Electrical Wiring Install the Cooktop Adjust the SwitchWarranty