Greenheck Fan Outdoor Air Ventilator manual Assemble Roof Curb, Locate and Cut Roof Opening

Page 9

Installation Instructions for:

CURB MOUNTING*

NV-90 and NV-120

*For installations using Greenheck's optional roof curb.

1. Assemble Roof Curb

Curbs are shipped knockdown and require assembly by others. Assembly instructions are also included with curb.

Assemble curb sections as shown using hex bolts and lock nuts supplied with curb.

Detail shown is typical for all four corners.

Roof Curb

 

 

41/2

2. Locate and Cut Roof Opening

241/4

 

When locating unit, make sure there is room to access unit

 

from all sides. Make sure inlet of this unit is located well

 

away from exhaust fans.

Recommended

405/8

Roof Opening

Roof Opening for NV-120 and NV-90 = (A) 36" x (B) 36"

(36"x36")

 

 

1031/2

3. Install Curb

 

Located curb over roof opening with dimensions shown to

 

the right and fasten in place.

 

 

431/4

Check that diagonal dimensions are within

 

± 1/8" of each other and adjust as necessary. Shim as

 

required to level.

 

A

813/16

 

B

 

4. Install Ductwork

DThe following chart shows the duct sizes and straight

Roof Opening

 

 

lengths recommended for optimal performance (AMCA

 

 

 

 

 

Publication 201-90). Using duct sizes less than

Ductwork

 

 

 

 

recommended lengths will affect fan performance. Good

by Others

 

 

C

duct installation practices should be followed for the

Roof Curb

 

 

 

 

remaining ductwork.

 

 

 

 

 

 

 

 

Duct Locations:

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

A

B

 

C

D

Straight

 

 

 

 

 

 

 

 

Duct Length

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

NV-90

24

93/8

 

24

301/4

81

 

 

 

 

 

 

NV-120

26

91/2

 

26

291/4

96

 

9

Image 9
Contents Greenheck Table of Contents Typical Installations Installation Instructions forMounting the Unit Attach Ductwork to Unit DischargeInstall Ductwork Install Roof Curb Equipment SupportNV-45 w/Downblast Discharge Roof OpeningComplete Installation Install Supply Unit1a. Slab Construction 1b. Install UnitCurb Mounting Rail MountingDischarge Opening Sizes Optional Up-stream Heating CoilInstall Curb Assemble Roof CurbLocate and Cut Roof Opening Detail a Install UnitInstall Birdscreen or Optional Weatherhood Filters Attach Support LegsAttach Weatherhood Electrical Instructions Sequence for wiring NV unitFor units without control centers For units with control centersSettings for Optional Components Air Volume Check and MeasurementSpecial Tools Required Check Voltage Check Blower RotationSteam Coils Instructions for CoilsMain Steam Direct Expansion CoilsCleaning Coil MaintenanceWater Coils FiltersBlower Unit Elevation View General Dimensions and WeightsWeeks after startup MaintenanceEvery 3 Months YearlyField Start-Up Documentation Maintenance Documentation