BASE INSTALLATION

PRELIMINARY ROUGH-IN

The floor structure beneath the unit must be able to support a total weight of the unit and bather. Refer to page 2, SPECIFICATIONS, for weight specifica- tions . Refer to COMPONENT IDENTIFICATION on page 4 to help identify parts.

STEP 1

Provide an opening in the subfloor no less than 5" x 5" square. This opening should be located on the center lines of the shower base drain hole.

C

L

C

L

2" WASTE PIPE

INSTALLATION INSTRUCTIONS

STEP 2

Remove the stainless steel strainer from the drain assembly. Disassemble the locknut and two gaskets from the back of the drain assembly. Apply a 1/4" bead of caulking (silicone) to the drain hole and insert the drain assembly. Replace the rubber washer, fiber washer, and lock nut in that order. Hand tighten the locknut. Remove excess sealant from finished side.

Apply a lubricant (common household liquid soap works well) to the inside of the rubber seal of the drain assembly.

STRAINER

APPLY LUBRICANT

SILICONE

DRAIN SEALANT ASSEMBLY

SHOWER BASE

RUBBER WASHER

5"X5" OPENING (MIN. AS POSSIBLE)

CAUTION: A nonflammable protective barrier must be placed between soldering work and base unit to

FIBER WASHER

STEP 3

NUT

prevent damage to the base.

STUD

WALL

COPPER FITTINGS

AND TUBING

NOT PROVIDED

45° COPPER ELBOW PROVIDED (2)

DETAIL 1

If the subfloor is level, no other preparation is neces- sary. You can proceed to install the shower base. If the subfloor is not level, level the subfloor by spreading floor leveling compound, mortar, plaster or minimal expan- sion structural foam with a minimum density of 5 lbs./ cubic feet EVENLY over ENTIRE area where base will be installed. The compound used MUST make contact with the entire bottom surface of the base. Both sides of a joint or splice of subfloor should be level to each other. Level and support waste pipe cutout area greater than 5" x 5". The base is NOT to be supported by the tile flange.

SPREAD MORTOR OR LEVELING

COMPOUND ETC EVENLY OVER ENTIRE AREA

5

Jacuzzi Whirlpool Bath© BY82000 03/05

Image 7
Contents Summer Rain Person Shower System ONE Wall Important Safety Information Contents Base Specifications SpecificationsROUGH-IN Reference Front View Side View Component IdentificationPreliminary ROUGH-IN Base InstallationCorrect Shim InstructionsClean UP After Base Installation With AIR Feature only Towers and Doors InstallationDetail a Attach air supply pipe to air tower plumbing Shower Base Slide fixed glass panel all the way into wall post Tower and Door Installation Towers and Door Installation Clean UP After Towers and Door Installation Operation Shower TowersAIR Tower Maintenance Tower Fixtures Repair Parts TOWER, 2 Person Shower Tower Plumbing Repair PartsJacuzzi Whirlpool Bath BY82000 03/05 Jacuzzi Whirlpool Bath National Headquarters Jacuzzi Whirlpool Bath Warranty Registration Card