Operation
Cycle Execution (Continued)
Wash
As soon as water level is reached (and any programmed temperature is reached), the displayed time begins counting down at
The machine will agitate low speed forward, pause, low speed reverse, pause, then repeat this sequence for the programmed time. The table below shows available agitation options.
Agitation Action Options
Agitation Type | Description |
12 seconds forward,
The cylinder accelerates to distribution speed seven seconds into the drain step. About five seconds later, the drain opens.
Note: The machine should drain in
30 seconds. If the machine fails to drain, contact a qualified service technician.
Spin
Spin steps for all segments except Fill 6 are
Normal
3 seconds pause,
12 seconds reverse,
3 seconds pause
3 seconds forward,
Intermediate spin steps can be 30 to 240
Gentle*
12 seconds pause,
seconds in length. Final spin steps can be from
3 seconds reverse,
12 seconds pause
*Gentle agitation information must be programmed in cylces 15 and 16.
Note: If the water does not reach the programmed temperature in 30 minutes, the computer will proceed with the cycle. (The time countdown will resume as though temperature had been reached, but the computer will continue heating).
Drain
The drain valve will open after the programmed segment time has elapsed. The cylinder will turn counterclockwise (forward) at wash speed while in the drain step. This counterclockwise direction mirrors the spin rotation and is, therefore, also considered forward.
18
1 to 10 minutes in length. Any spin step can be skipped by programming 0 for the spin time. However, in order to have a high speed spin in the Fill 6 segment, a nonzero time must be programmed for that segment.
Note: An automatic
If the cycle program segment spin time is set to zero, the computer moves to the next segment of the cycle program. If the segment is at the end of a cycle program, the computer goes into the stop routine.
F232061