Installation and Commissioning
Voice Gateways System Manual 11
2.3 Installation and CommissioningThe unit can be placed on a desktop or a shelf. The location should be selected
taking into account the necessary connections to mains power, SU-IDU and user's
data/telephony equipment.
It is assumed that installation and commissioning of the SU has already been
completed and that the SU is connected to the Base Station.
1Connect the DC power cable of power supply to the 12 VDC jack on the rear
panel of the unit.
2Connect the mains power cable to the power supply. Connect the other end of
the mains power cable to the AC mains.
3After power up, all front panel LEDs bilnk once, and then the PWR, WAN and
LAN LEDs bilnk twice, indicating that the unit operates properly. Then the
PWR LED is lit. Other LEDs may also be lit, according to the status of the
WAN, LAN and Phone ports, as described in Section 2.2.3.
4Connect a PC to the WAN or LAN port using a crossed Ethernet cable.
Configure the PC with a static IP address 192.168.254.2 and subnet mask
255.255.255.0. (The IP address of the WAN port for management purposes
only is 192.168.254.254 and netmask 255.255.255.0)
5Open a web browser and connect to the unit by entering
http://192.168.254.254. in the address field.
To install the Voice Gateway:
NOTE
The color codes of the power cable are as follows:
Brown Phase ~
Blue Neutral 0
Yellow/Green Ground
NOTE
The VG can be accessed via the WAN or LAN port using the WAN IP address.