![](/images/new-backgrounds/1264900/26490029x1.webp)
Top Cable Entry
Preparing for top cable entry (Default)
Cable entry in Top Cover of Input/Output Section.
| Top view |
|
|
| M6 Bolt |
| DC | DC |
| cable | cable |
| entry | entry |
| AC IN cable | AC OUT |
| entry | cable entry |
|
BAT 1 BAT 2
Top view
AC IN | AC OUT | ||
90 | L3 IN | 95 | L3 OUT |
91 | L2 IN | 94 | L2 OUT |
92 | L1 IN | 93 | L1 OUT |
1.75 in / | 1.75 in / | |
44.45 mm | ||
44.45 mm | ||
| ||
| 2.3 in / 58 mm |
IN/OUT power cable (top entry)
L1 IN | L1 OUT |
92 | 93 |
L2 IN | L2 OUT |
91 | 94 |
L3 IN | L3 OUT |
90 | 95 |
N | N |
Loosen the 8 bolts in both cable entry covers (4 bolts in each cover). Drill holes for the grommets in areas shown. Install the grommets and
Install cable lugs on busbars. Use M12 bolts. Feed cables through the top grommets.
Connect L1, L2 and L3 to busbars where indicated.
Symmetra MW 800 kW 3 × 400/230 V Installation - | 9 |