Prepare for Cables

Note: Ensure that the unit is in its final location prior to installation.

Prepare for Cables

Bottom cable entry

Installation

MGE™ Galaxy™ 3500

10-40 kVA 380/400/415 V with batteries

Note: Battery and utility/mains power must not be connected until all other wiring has been completed.

See Also: For parallel configurations see manual 990- 3568.

Level the Enclosure

Warning: The system must be installed on a level floor. The leveling feet will stabilize the enclosure, but will not account for a badly sloped floor.

From the rear of the UPS, loosen the six M4 screws from the upper cover (the cable landing area) on the back and remove.

UPS

UPS

XR battery enclosure

IMPORTANT SAFETY INSTRUCTIONS

SAVE THESE INSTRUCTIONS

Warning: ALL safety instructions in the Safety Sheet (990-2940) must be read, understood, and followed when installing the UPS system. Failure to do so could result in equipment damage, serious injury, or death.

Warning: After the UPS has been electrically wired, do

Use a 13/14 mm wrench to adjust the four leveling feet.

Ensure that the system is level.

Caution: Do not move the enclosure after the leveling feet have been lowered.

Floor Anchoring (if applicable)

Anchor the UPS enclosure to the floor

Note: Floor-anchoring bolts are not provided with the UPS.

Purchase the bolts locally (minimum size: M8). Follow the specifications given by the manufacturer of the floor anchoring system when bolting the UPS system to the floor.

Route the cables from the slanted back plate, up through the punched bracket, and into the cable landing area.

Fasten the cables with cable ties

not start it up. Start-up is commissioned to authorized personnel from Schneider Electric.

Caution: All electrical power and power control wiring must be installed by a qualified electrician, and must comply with local and national regulations for maximum power rating.

Reuse the two transport brackets (one on each side) that were used to secure the UPS to the pallet during transport.

Drill two to six holes in the floor for each bracket. Attach with bolts.

Note: A conduit box (part no. SUVTOPT001 or SUVTOPT002) is available as an option.