Bard P1060A1, P1148A1, P1142A3 Location, Typical Installations, Wet Coil Cooling

Models: P1060A1 P1142A3 P1148A1

1 23
Download 23 pages 2.84 Kb
Page 8
Image 8
INSTALLATION

INSTALLATION

LOCATION

GENERAL

The unit must be located outside, or in a well ventilated area. It must not be in the space being heated or cooled. A sound absorbing material should be considered if the unit is to be installed in such a position or location that might cause transmission of sound or vibration to the living area or adjacent buildings.

SLAB MOUNTING

In areas where winter temperatures DO NOT go below 32° F for periods over twelve hours, the unit may be slab mounted at grade level. When installing unit at grade level, install on a concrete slab at least four inches above finished grade level. Slab should have a slope tolerance away from the building structure of at lease 1/4 inch per foot, while being level from side to side. Place slab in a location where runoff water from higher ground will not collect around unit. See Figure 3.

A minimum of 18 inches should be provided between the coil inlet and any building surfaces. Provide at least four feet between coil outlet and any building wall, fences or other vertical structures. Provide a minimum of three feet clearance on the service access side of the unit. See Figure 4

ROOF MOUNTING

When a unit is installed in areas where low ambient temperatures or strong winter winds exist, it should be placed for prevailing winter winds are not in direct line with the outdoor coil. If this is not possible, a wind barrier should be constructed. Place barrier 24 inches from the coil inlet side of the unit and in the direction of prevailing winds. Size barrier at least the same height and width as the unit. This may be necessary on ground level installations, also. See Figure 5.

WINTER INSTALLATION BELOW 32°F

In areas where winter conditions go below 32°F for extended periods, the unit must be elevated above the mounting surface to prevent snowfall or ice accumulation from interfering with the operation of the unit. A minimum of twelve inch elevation is recommended, while greater elevation may be required for areas of high snow accumulation. Poured concrete, steel framework, brick, cement block, etc., can be utilized to construct a suitable raised mounting platform. See Figure 6.

DUCT WORK

Refer to Tables 4, 5 and 5A when designing duct work for maximum static pressure available with the specific model and heater package being installed.

TABLE 5

RATED CFM AND

EXTERNAL STATIC PRESSURE (ESP)

WET COIL (COOLING)

 

Rated

Rated

Recommended

Model

CFM

ESP

Air Flow Range

 

 

 

 

P1142A3

1400

.20

1260 - 1540 CFM

 

 

 

 

P1148A1

1550

.40

1400 - 1700 CFM

 

 

 

 

P1060A1

1700

.20

1530 - 1870 CFM

 

 

 

 

TABLE 5A

ESP

P1142A3

P1148A1

P1060A1

Inches

PH11421

PH1048

PH1060

H2O

Dry / Wet

Dry / Wet

Dry / Wet

0

1650 / 1625

1950 / 1920

1850 / 1850

.1

1550 / 1525

1860 / 1830

1800 / 1780

.2

1435 / 1400

1780 / 1750

1725 / 1700

.3

1340 / 1310

1680 / 1660

1660 / 1625

.4

1230 / 1210

1580 / 1550

1580 / 1540

.5

1120 / 1100

1500 / 1480

1500 / 1475

 

 

 

 

TYPICAL INSTALLATIONS

1.ROOF MOUNTED – The unit is mounted on a sturdy base on the roof of the building. Return air to the unit is brought through a single return grille (grilles with built-in filters are best since they enable easy access for filter changing). Return air ducts are attached to the lower section of the front panel.

Supply air is brought from the unit to attic duct work or to a furred down hall. Supply air duct is attached to the top of the front panel.

CAUTION: All outdoor duct work must be thoroughly insulated and weatherproofed. All attic duct work must be thoroughly insulated. Two inch thick insulation with suitable vapor barrier is recommended for both outdoor and attic runs.

In roof top installation, as in all installations, the air conditioner must be level from side to side. However, the unit should have a pitch along the length to assure complete external drainage of precipitation and of defrost condensate.

2.CRAWL SPACE – Duct work installed in crawl space must be well insulated and provided with a vapor barrier. In addition, the crawl space must be thoroughly ventilated and provided with a good vapor barrier as a ground cover. It is most desirable to install the unit will be outdoors rather than inside the crawl space, so that it will be readily accessible for service.

Manual 2100-324 Page 6

Page 8
Image 8
Bard P1060A1 Location, Typical Installations, Table Rated Cfm And External Static Pressure Esp, Wet Coil Cooling