Chapter 3: Preparing the Cabinet for Installation

3. Preparing the Cabinet for Installation

Follow these simple recommendations for best performance from your new enclosure.

3.1 Handling

NOTE: For palletized cabinets, see the unpacking instruction sheet before attempting to remove the cabinet from the pallet.

To achieve the level of acoustic performance and industrial needs of a high-quality 19” enclosure, the composition of cabinet parts means that the QuietCab cabinets are very heavy. When moving the cabinet, we recommend that a minimum of two people carry out this task.

3.2 Tools You Will Need

10-mm ratchet and socket

Phillips screwdriver

Utility knife

Level

Cage nut tool

3.3 Adjusting the Doors

The QuietCab cabinet’s doors are aligned before they leave the factory. But in case they need adjustment, follow these instructions.

Side-to-side adjustment

Turning the front screw on the hinge counterclockwise will move the door closer to the corresponding side panel. Turning the screw clockwise will move the door toward the opposite side panel.

Front-to-back adjustment

Loosening the back screw will allow the hinge to be adjusted frontward or backward. Tighten the screw after adjustment.