Installing the PFC3B

Figure 6 Installing the Supplied Screws

105311

Note To use the PFC3BXL, you must also upgrade the switch processor (SP) and route processor (RP) memory on the Supervisor Engine 720 to 1 GB each using the included DRAM DIMMs. For information on upgrading the memory on the Supervisor Engine 720, refer to the Supervisor Engine 720 Switch Processor and Route Processor Memory Installation Note at this URL:

http://www.cisco.com/univercd/cc/td/doc/product/lan/cat6000/cfgnotes/78_15538.htm

The Supervisor Engine 720 memory upgrade (MEM-MSFC2-1GB=) is an option when using the PFC3B.

Step 6 If you installed a PFC3BXL, upgrade the SP and RP memory on the Supervisor Engine 720 if you have not done so already.

Step 7 Install the Supervisor Engine 720 in the Catalyst 6500 series switch. (Refer to the Catalyst 6500 Series Switch Module Installation Guide for installation instructions.)

Caution The hardware on both supervisor engines in a single chassis must be identical. If you have redundant supervisor engines, you must install the PFC3B or PFC3BXL on each Supervisor Engine 720.

Step 8 If you are installing a PFC3B on a redundant Supervisor Engine 720, go to Step 3 in the “Preparing the Supervisor Engine 720” section on page 5 and follow the procedure for removing the supervisor engine.

Step 9 Power up the switch.

Catalyst 6500 Series PFC3B and PFC3BXL Installation Note

 

78-16220-02

11

 

 

 

Page 11
Image 11
Cisco Systems WS-F6K-PFC3B=, WS-F6K-PFC3BXL= manual Installing the Supplied Screws