31
3-Phase Units
WATTS VOLTS PHASE WIRES CYCLE AMPS SUPPLY CONNECTION HEATER RATED
HERTZ WIRE SIZE (COPPER) VOLTAGE
6400 208 3 3 60 17.8 12 208
5440 220 3 3 60 14.3 14 (12 recommended) 240
6400 240 3 3 60 15.4 14 (12 recommended) 240
9400 208 3 3 60 26.1 10 208
7960 220 3 3 60 20.9 10 240
9400 240 3 3 60 22.6 10 240
1-Phase Units
WATTS VOLTS PHASE WIRES CYCLE AMPS SUPPLY CONNECTION HEATER RATED
HERTZ WIRE SIZE (COPPER)>VOLTAGE
6400 208 1 2 60 30.8 8 208
5440 220 1 2 60 25 10 240
6400 240 1 2 60 26.7 10 240
9400 208 1 2 60 45.2 6 208
> For supply connection use only copper wire suitable for at least 75° C (167° F).
C. STARTUP AND CHECKOUT
The Startup and Checkout procedure prepares a recently installed or repaired steamer for operation. The
procedures check proper installation and electrical connection of the steamer, and verify basic steamer
operation.
1. Installation Checkout
Use the Installation Checklist Table 4-2, to check the overall installation.
Table 4-2. Installation Check List
TASK REFERENCE COMPLETED
Preparation Page No.
Verify electric power requir ements 30 _____
Check operating location clearances 20 _____
Verify Field Assembly of Unit 24-26 _____
Verify Field Assembly of Stand (if applicable) 21-24 _____
Installation
Verify Steamer is Leve l 25 _____
Check drain line conne ction 26 _____
Check water supply connection 27 _____
Test water supply lines 29 _____
Check electrical line connection 29 _____
Perform Startup and checkout 31 _____
Notes on installation:
Table 4-1 Minimum Wire Requirements