Installation Instructions
5.Drill the mounting holes...
If mounting the hood to brick or masonry:
•Drill five 5/16” X 1 1/2” holes in the locations marked.
•Insert five of the provided wall anchors into the five holes. The anchors provided are for attaching the hood to masonry or brick only.
MOUNTING
BRACKET
ANCHOR
“L”
BRACKETS
TEMPLATE
Mounting to brick or masonry
If mounting the hood to drywall:
•Drill five appropriate sized holes for the mounting hardware being used. The drywall mounting hardware must be purchased separately.
MOUNTING BRACKET
TEMPLATE
“L” BRACKETS
Mounting to drywall or plaster
6.Attach the blower assembly mounting bracket and the “L” brackets securely to the wall (5 places).
Install the Duct Work
IMPORTANT - The installed duct work must:•Be centered on the vertical center line drawn on the wall.
•Fit flush into the half circle on the chimney mounting bracket, if the duct work is to enter the chimney through the ceiling rather than through the back wall).
•Extend down as far as the top of the blower assembly mounting bracket.
DUCT THROUGH
CEILING (OPTION 1)
CHIMNEY MOUNTING
BRACKET
WALL
DUCT THROUGH BACK
WALL (OPTION 2)
END OF DUCT,
EVEN WITH TOP OF
BLOWER ASSEMBLY
MOUNTING BRACKET
“L” BRACKET
Duct tape all joints