Desa CGFP28PT Built-Infireplace Installation, Check Local Building Codes, Continued

Models: CGFP28PT CGFP28P

1 34
Download 34 pages 26.05 Kb
Page 13
Image 13
BUILT-IN FIREPLACE INSTALLATION

OWNER’S MANUAL

INSTALLATION

Continued

9.If using an optional blower, install it now. Follow instructions provided with the blower.

10.Connect fireplace to gas supply (see Connecting Fireplace To Gas Supply, page 15).

11.Check all gas connections for leaks. See Checking Gas Connections, pages 15 and 16.

12.After heater is secured, replace mantel on hearth base (see Figure 25). Make sure mantel is flush against wall. In- stall brass trim (see page 7).

Figure 24 - Inserting Fireplace Into Cabi- net Mantel

BUILT-IN FIREPLACE INSTALLATION

(Check Local Building Codes)

Built-in installation of this fireplace involves installing fireplace into a framed-in enclo- sure. This makes the front of fireplace flush with wall. An optional brass trim accessory is available (see Accessories, page 32). The brass trim will extend past the sides of the fireplace approximately 1/2". This will cover the rough edges of the wall opening. If installing a mantel above the fireplace, but you must follow the clearances shown in Figure 29, page 14. Follow the instructions below to install the fireplace in this manner.

 

Actual

Framing

 

 

 

Height

32 3/8"

33"

Front Width

34 5/16"

34 3/4"

Depth

16 11/16"

17 3/4"

1.Frame in rough opening. Use dimen- sions shown in Figure 26 for the rough opening.

If installing in a corner, use dimensions shown in Figure 27 for the rough open- ing. The height is 33" which is the same as the wall opening in Figure 26.

2.If using optional blower, install it now. Also install and properly ground GA3555 three prong 120 volt outlet in fireplace. Follow instructions included in kits.

3.Install gas piping to fireplace location. This installation includes an approved flexible gas line (if allowed by local codes) after the manual shutoff valve. The flexible gas line must be the last item installed on the gas piping. See In- stalling Gas Piping to Fireplace Loca- tion, page 14.

4.Carefully set fireplace in front of rough opening with back of fireplace inside wall opening.

5.Attach flexible gas line to fireplace gas regulator. See Connecting Fireplace to Gas Supply, page 15.

6.Carefully insert fireplace into rough opening.

7.Attach fireplace to wall studs using nails or wood screws through holes in nailing flange (see Figure 28).

8.Check all gas connections for leaks. See Checking Gas Connections, pages 15 and 16.

9.If using optional GA7090 Brass Trim Kit, install brass trim after final finish- ing and/or painting of wall (see Figure 6, page 7).

Cabinet Mantel

 

 

 

 

 

 

Nails or

 

 

 

 

 

 

 

17 3/4"

 

 

 

 

 

 

Wood

 

 

 

 

 

 

 

 

 

 

 

 

33"

 

 

 

 

Screws

 

 

 

 

 

 

 

 

 

 

 

 

(Check Local Building Codes)Manual background 34 3/4"Manual background

Figure 26 - Rough Opening for Installing in Wall

39 3/8"

27 7/8"

Figure 25 - Installing Cabinet Mantel

Manual background 34 3/4" 55 5/8"

Figure 27 - Rough Opening for Installing in Corner

Nailing

Flanges

Figure 28 - Attaching Fireplace to Wall Studs

Continued

103414

13

Page 13
Image 13
Desa CGFP28PT installation manual Built-Infireplace Installation, Check Local Building Codes, Continued