8
Framing
Installing Transition Pipe and Starter Collar
PRE-INSTALLATION
PREPARATION
Continued
FRAMING
1.Frame appliance enclosure as illustrated in Figures 7 and 8.
Note: If a wall covering is used to line the enclosure, then all measurements must be from the surface of the covering.
2.Place the appliance into the framing and secure it.
Note: If appliance is to be raised above floor level, a platform must be built to support the appliance.
3.Install the supply line to the appliance using a 1/2" NPT black iron gas line terminating 2 5/16" above the bottom of the appli- ance. The gas line must be installed through the lower left side access point or alternate access hole in the bottom of the appli- ance (see Figure 19, page 12).
4.Repack insulation around the gas line to cover any remaining openings in the conduit sleeve. Prepare the incoming gas line with teflon tape or pipe joint compound and
Note: If 1/2" NPT black iron pipe does not mate with fitting at the end of flexible gas line, remove fitting and replace with a 37 degree flare
These Dimensions Allow for a 3/4" Clearance at Sides and Back of Fireplace. However, 0" Clearance is Permitted
D
C
A | 3/4" Clearance | ||
Not Required | |||
|
| ||
|
| at Nailing | |
|
| Flanges | |
|
|
B
| M36(B,H)/VM36(B,H) | M42(B,H)/VM42(B,H) |
A | 24 1/2"(622.3mm) | 27 9/16"(700.1mm) |
B | 73 7/8"(1876.4mm) | 83 7/8"(2130.4mm) |
C | 52 3/16"(1326mm) | 59 5/16"(1506.6mm) |
D | 17 1/4"(438.2mm) | 19 1/2"(495.3mm) |
|
|
|
Figure 8 - Corner Installation Guidelines
WARNING: When finishing appliance, do not overlap combustible material onto the black front face. Brick, tile, or other noncombustible materials may be applied to the face provided that any gap is between the material used and the face is caulked with a noncombustible caulking.
|
| A |
| B |
|
| C |
|
| M36(B,H)/VM36(B,H) | M42(B,H)/VM42(B,H) |
A | 40 3/8" (1020mm) | 44 3/8" (1121mm) |
B | 21 3/8" (543mm) | 23 1/8" (587mm) |
C | 41 1/4" (1048mm) | 48 1/4" (1226mm) |
Figure 7 - Rough Opening for Installing in Wall
INSTALLING TRANSITION PIPE AND STARTER COLLAR
The transition pipe and starter collar shown in Figure 9 are supplied with the fireplace, unattached and ready for installation. Remove the starter collar and set aside. Slide the transition pipe over the vent collar and attach with a minimum of three screws. Replace the starter collar over the transition pipe and attach using four screws located on the leg stands (five used on the model M42). To install
Starter Collar
Transition Pipe
Vent Collar
Figure 9 - Installing Transition Pipe and Starter Collar
For morevisit www..com