Installation |
Installation
The ASCO 7000 Series
Refer to the manual from the manufacturer of the
Supporting Structure
The supporting foundation for the enclosure must be level and straight. Refer to the applicable enclosure outline drawing included with the transfer switch for all mounting details including door opening space.
Mounting
Refer to the outline and mounting diagram and mount the automatic transfer switch according to details and instructions shown on the diagram.
NOTICE
Protect the transfer switch from construction grit and metal chips to prevent malfunction or shortened life of the transfer switch.
Testing Power Conductors
Do not connect the power conductors to the transfer switch until they are tested. Installing power cables in conduit, cable troughs, and
Line Connections
Refer to the wiring diagram provided with the transfer switch. All wiring must be made in accordance with the National Electrical Code and local codes.
!DANGER
Engine-Generator Control
Connections
All customer connections, including the engine control contact connections, are located on terminal block TB. This terminal block is located on the interior left side of the control section. Refer to the wiring diagram provided with the automatic transfer switch. Connect the engine start wires to the appropriate terminals. See Figure
Table A.
When normal source fails | TB terminals |
contact closes | TB1 and TB2 |
contact opens | TB1 and TB3 |
engine-
generator1 control
contacts2
3
Figure
Auxiliary Circuits
Connect auxiliary circuit wires to appropriate terminals on terminal block TB as shown on the wiring diagram provided with the automatic transfer switch.