Installation Instructions

Installation Instructions

PREPARE HOT WATER LINE

The line may enter from either side, rear or floor within the shaded area shown in Figure F.

The line may pass through the same hole as the electrical cable and drain hose. Or, cut an additional 1-1/2" dia. hole to accommodate the water line. If power cord with plug is used, water line must not pass through power cord hole.

PREPARE HOT WATER LINE CAUTION:

The hot water supply line pressure must be at least 20 psi. Lower pressures could cause the water valve to leak and cause water damage.

 

BEFORE YOU BEGIN

STOP

Locate and set aside the package containing

2 Phillips head countertop mounting screws

 

 

and 2 additional toekick screws (located in

 

the literature package).

STEP 1 CHECK DOOR BALANCE

To check the door balance, hold the top of the dishwasher firmly.

Open the door slowly. If the door drops when released, you will need to increase spring tension. If the door closes when released, you will need to decrease tension.

If adjustments are needed, see Step 1A. If no adjustments are needed, skip to Step 2.

Shut-off

1-1/2" Dia.

Valve

Hole

 

Hot

 

2"

 

From

18" From Wall

Cabinet

 

STEP 1A ADJUST DOOR SPRINGS

(IF NECESSARY)

FOR ZBD1870 MODELS

For ZBD1850 models, refer to the instruction provided on the template packed with that model.

To adjust the door springs, you will need to remove the dishwasher side panels.

Cabinet FaceSTOP

Figure F

3" From Floor

To remove the side panels:

• Remove the screws from the top and back of each

dishwasher side panel, sixteen screws total. Open the door

Water Line Connection

Turn off the water supply.

Install a hand shut-off valve in an accessible location, such as under the sink. (Optional, but strongly recommended and may be required by local codes.)

Water connection is on the left side of the dishwasher. Install the hot water inlet line, using no less than 3/8" O.D. copper tubing. Route the line as shown in Figure F and extend forward at least 18" from rear wall.

Adjust water heater for 120°F to 150°F temperature.

Flush water line to clean out debris.

The hot water supply line pressure must be 20-120 PSI.

STEP 1 CHECK DOOR BALANCE CAUTION:

Opening the door will cause the dishwasher to tip forward. Do not open the door until you are ready

to install the dishwasher. If it is necessary to open the door, hold the top of the dishwasher securely with one hand and hold the door with the other hand.

and remove the four screws securing the panels to the inside

door frame.

Screws

Screws

ScrewsScrews

Screws

Front

Rear

Figure G