Guardian Technologies 04456-2, 04389-2, 04390-2 Break-In Procedure, Automatic Transfer Operation

Models: 04390-2 04456-2 04389-2

1 60
Download 60 pages 41.21 Kb
Page 16
Image 16
3.2USING THE AUTO/OFF/MANUAL SWITCH (FIGURE 3.1)

Section 3 — Operation

Guardian Air-cooled 7 kW, 12 kW and 15 kW Generators

NOTE:

The access panel on top of the control panel must be removed to adjust the voltage regulator.

NOTE:

3.2USING THE AUTO/OFF/MANUAL SWITCH (FIGURE 3.1)

‹3.2.1 “AUTO” POSITION

The voltage regulator is housed above the genera- tor's control panel. The regulator maintains a volt- age in direct proportion to frequency at a 2-to-1 ratio. For example, at 62 Hertz, line-to-neutral voltage will be 124 volts.

Selecting this switch position activates fully automat- ic system operation. It also allows personnel to start and exercise the engine every seven days with the set- ting of the exercise timer (see Section 3.6). This posi- tion also is used for remote starting, when it is set up.

3.1BREAK-IN PROCEDURE

Once the unit has been installed and all electrical checks have been made, it is strongly recommended that the following “Break-in Procedure” be completed to ensure correct generator operation in the future.

1.

Set the generator’s AUTO/OFF/MANUAL switch to

 

AUTO.

2.

Turn OFF the utility power supply to the transfer

 

switch using the means provided (such as a utili-

 

ty main line circuit breaker).

3.

The unit will start, and the transfer switch will

 

transfer to standby.

‹3.2.2 “OFF” POSITION

This switch position shuts down the engine. This position also prevents automatic operation.

‹3.2.3 “MANUAL” POSITION

Set the switch to MANUAL to crank and start the engine. Transfer to standby power will not occur unless there is a utility failure.

Figure 3.1 – Generator Control Panel

4.

Using the transfer switch’s built-in emergency

 

load center, turn on circuits to load the generator

 

to approximately 25% rated load and run the unit

 

for one hour.

5.

Run the unit for one hour at 50% rated load.

6.

Run the unit for one hour at 75% rated load.

7.

Run the unit for one hour at 100% rated load.

8.

Turn ON the utility power supply to the transfer

 

switch, which will allow the transfer switch to

 

transfer back to utility power. The unit will con-

 

tinue to run for one minute and then shut down.

FUSE

5A

AUTO OFF MAN.

FUSE

15ASET EXERCISE

TIME

L o c a t e y o u r n e a r e s t ‹3.2.1 “AUTO” POSITION3.1BREAK-IN PROCEDURE‹3.2.2 “OFF” POSITION d e a le r a t :

‹3.2.3 “MANUAL” POSITIONPOWER SYSTEMS, INC.

SYSTEM SET

LOW OIL

HIGH TEMP.

OVER SPEED

OVER CRANK

F L A S H IN G G R E E N L E D =

N O U T IL IT Y S E N S E 4 F L A S H IN G R E D L E D S =

E X E R C IS E R N O T S E T

9.

Allow the unit to cool.

10.

Set the generator’s main circuit breaker to its

 

OFF (or open) position.

11.

Set the generator's AUTO/OFF/MANUAL switch to

 

OFF. Remove the 5A and 15A fuses from the gen-

 

erator control panel. Disconnect the battery

 

cables as outlined in “General Hazards” (page 2).

12.

Drain the oil and remove the oil filter. Replace the

 

oil filter according to Section 4.4, “Changing the

 

Oil Filter”. Replace the oil with synthetic oil as

 

recommended in Section 4.3, “Changing the

 

Engine Oil”.

13.

Reconnect the battery cables as outlined in

 

“General Hazards” (page 2) and insert the 5A and

 

15A fuses into the generator control panel. The

 

generator is now ready for service.

14 Generac® Power Systems, Inc.

With the switch set to AUTO, the engine may

!crank and start at any time without warning. Such automatic starting normally occurs when utility power source voltage drops below a pre- set level or during the normal exercise cycle. To prevent possible injury that might be caused by such sudden starts, always set the switch to OFF and remove the fuses before working on or around the generator or transfer switch. Then, place a “DO NOT OPERATE” tag on the generator panel and on the transfer switch.

3.3AUTOMATIC TRANSFER

OPERATION

To select automatic operation, do the following:

1.Make sure the transfer switch main contacts are set to their UTILITY position, i.e., loads connect- ed to the utility power source (Figure 3.2).

2.Be sure that normal UTILITY power source volt- age is available to transfer switch terminal lugs N1 and N2.

Page 16
Image 16
Guardian Technologies 04456-2 Break-In Procedure, Automatic Transfer Operation, Using The Auto/Off/Manual Switch Figure