3
Figure 4. Plunger insertion
NOTE: All steps required for installation of the ame controller
MUST be done by a quali ed gas service technician.
FLAME CONTROL
SOLENOID
REGULATOR
TOWER
PLUNGER
JAM NUT
REMOTE
RECEIVER Line cord
from fan
LEARN 110/120 VAC, 3A
(Receptacle on back)
Alternative Wiring for units with a wall switch
Disconnect the wall switch wire from the TH terminal on
the valve and connect this wire to male connector supplied
on the receiver. Connect remaining female connector from
receiver to the TH terminal on the valve.
Adding Optional Fan/Blower
Plug 2-prong fan cord directly into the 3 prong polarized
plug on the back of the receiver (see Figure 3). This
receptacle output is 110/120 VAC, 3 AMP.
Figure 3. Adding Fan/Blower
Installing Regulator Tower
NOTE: A manometer MUST be used to set the manifold
pressure on the gas valve.
1. Using a Torx T20, or slotted screwdriver, remove and
discard the three pressure regulator mounting screws
(A), pressure regulator tower (B), and the spring and
diaphragm assembly (C) See Figure 5.
2. Ensure the rubber gasket (D), which is pre- tted as
part of assembly (E), is properly positioned and install
the new pressure regulator tower using the supplied
screws (F). Tighten screws securely (Reference torque
= 25 lb-in.) and remove cover screw (G).
3. Insert the correct plunger into the ame control
solenoid (BLUE = NATURAL GAS, RED = PROPANE).
See Figure 4.
A
F
G
B
C
D
E
Figure 5. Installing Regulator Tower