OM-478 Page 16
SECTION 4 INSTALLATION

4-1. Installing Welding Generator

install1 12/99 Ref. ST-800 652 / Ref. ST-800 477-A / ST-158 936-A / S-0854
1
2
Electrically bond generator frame to
vehicle frame by metal-to-metal
contact.
GND/PE
34
Always ground generator
frame to vehicle frame to pre-
vent electric shock and static
electricity hazards.
1 Generator Base
2 Metal Vehicle Frame
3 Equipment Grounding
Terminal
4 Grounding Cable
Use #10 AWG or larger insulated
copper wire.
If unit does not have GFCI re-
ceptacles, use GFCI-
protected extension cord.
2
OR
18 in
(460 mm)
18 in
(460 mm)
18 in
(460 mm) 18 in
(460 mm)
18 in
(460 mm)
OR
Movement Airflow Clearance Location
Grounding
OR
Do Not Lift Unit From End

4-2. Connecting The Battery

1/2 in

+

Connect Negative ()
Cable Last.
Tools Needed:
ST-153 654-B / Ref. ST-184 780-C / Ref. S-0756-B