STEP 7 (See Diagram 7 & Lower Cable Loop Diagram)
A.) Attach the 164” Lower Cable (#35) to the opening on the Leg Developer (#8). Attach a Pulley (#47) to the opening. Secure it with one M10 x 2 ½” Allen Bolt (#84), two ∅ 7/8” Leg Developer Pulley Bushings (#52), and one M10 Aircraft Nut (#91).
B.) Draw the Cable underneath the Pulley to the open bracket on the Front Base Frame (#12). Attach a Pulley to the bracket. Secure it with one M10 x 1 ¾” Allen Bolt (#83), two ∅ ¾” Washers (#92), and one M10 Aircraft Nut (#91).
C.) Draw the Cable underneath the Pulley towards the back of the machine through the bottom opening on the Vertical Frame (#4) to the open bracket on the Rear Base Frame (#14).
D.) Install a Pulley to the bracket with M10 x 1¾” Allen Bolt (#83), two Ø ¾” Washers (#92), and one M10 Aircraft Nut.
E.) Draw the Cable underneath the Pulley then pull upward to the Double Floating Pulley Bracket (#22) with previously installed in
F.) Draw the Cable around the Pulley then downward. Attach the Cable to an Angled Double Floating Pulley Bracket (#27). Repeat Procedure D above to install a Pulley. Let the Bracket hanging for now.
G.) Draw the Cable around the Pulley then upward to the opening on the Vertical Frame (#4). Attach a Pulley to the opening. Secure it with one M10 x 3 ½” Allen Bolt (#77), two Pulley Bushings (#49), and one M10 Aircraft Nut (#91).
H.) Insert the Cable through a Ball Stopper (#76). Attach the Cable to a
18