7.3Electrical connection
Make the electrical connection only after the hydraulic connection has been completed; set up the motor control system in conformity with the technical standards and regulations in force (EN
Check that the main frequency and voltage and the available power are suitable for the motor installed. All the material used for the electrical connection (cables, cable clamps, switches and shielding) must have a suitable level of protection for the environment in which it is installed.
Be sure to use cables of sufficient
When starting, the motor’s current absorption increases briefly to
Johnson Pump will accept no responsibility for damage to property and/or injury to persons caused by failure to comply with technical standards and regulations in force.
Lower | Higher |
voltage | voltage |
Fig 2
8.0Operation
8.1Preliminary operations and starting
When first starting, fill the pump with liquid so as to create the pressure drop required for suction. When starting subsequently the quantity of liquid that remains in the pump will be sufficient to ensure
•Check that the pump turns freely under hand pressure.
•Check that the clamp joining the pump casing and the cover is well tightened and that
it cannot be easily unscrewed by hand. The tightening of the clamp must be carried out by means of a key and not by hand.
•Check that the pump turns in the market direction.
•Check that any gate valves installed on the suction and discharge pipelines are open.
•Start the pump and check the turns direction; before restarting it is extremely important to
7 |