16 NOTE: DIAGRAMS & ILLUSTRATIONS ARE NOT TO SCALE.
CAUTION: Wear gloves during brick installation in case of
sharp edges inside the stove.
WARNING: IF THE BRICKS ARE NOT INSTALLED EXACTLY AS
SHOWN BELOW, THEY COULD FALL OUT OF PLACE DURING
REFUELING OR BURNING OF THE STOVE CAUSING SERIOUS
INJURY.
BRICK AND BAFFLE INSTALLATION
Firebox Brick Layout as
Viewed from the Front
Figure 19
Figure 20 - Baffle Boards Installed Figure 21 - Baffle Boards
Letter A Brick Are Full Size
9” (229mm) Long x
4-1/2” (114mm) Wide x
1-5/16” (33mm) Thick
6.5
7.7
Back Baffle Board
Back Baffle Board
7.7”
(196mm)
6.5”
(165mm)
Front Baffle Board
Front Baffle Board
1. Install firebox bottom brick spacers on both the left and right side of
firebox. The brick spacers are located in the package with the manual.
Assure that brick spacers are pushed to each side until they are in
full contact with the firebox side on each side.
2. Install brick #1-20 in the numbered sequence shown in Figure 19.
3. Brick’s 13 and 14 will be located between the steel firebox and rear
baffle board (already installed).
4. Once all bricks are installed confirm that the already installed baffle
boards are in there correct location and resting on the secondary
burn tubes.