14
55
15
54
18
17
G
20
16
11
19
26
59
STEP 5:
Use the following hardware contained in Blister Pack (7-3):
M10 x 50mm HEX TENSION SCREW (Qty. 4)
GUIDE ROD RETAINER (Qty. 4)
RETAINER RING (Qty. 4)
NOTE: INSTALL FROM THE INSIDE OF THE UNIT.
Position two WEIGHT STACK CUSHIONS (20) and GUIDE RODS (16)at the GUIDE ROD BRACKET (G) on the
RIGHT TOWER(11) as shown.
NOTE: MAKE SURE THAT THE PLUGGED END OF THE GUIDE RODS(16) ARE FACING UP.
Slide one WEIGHT PLATE (17) over the GUIDERODS (16) and slowly lower the WEIGHT PLATE (17) onto the
WEIGHT STACK CUSHIONS (20).
Continue stacking a total of fifteen WEIGHTPLATES (17).
Slide one TOPPLATE (18)over the GUIDE RODS (16) and slowly lower it onto the WEIGHT PLATES (17).
Slide one WEIGHT PIN withRING (26) over the stem of the TOPPLATE (18).
Thread the HEAD PLATEPULLEY ASSEMBLY(19) into the TOPPLATE (18). Do not tighten! This will be adjusted
later. Make sure the JAMNUT (59) is threaded onto the HEAD PLATE PULLEYASSEMBLY (19)before threading
into the TOPPLATE (18).
Slide one RETAINER RING(54) over each of the GUIDE RODS (16).
Thread an M10 x 50mm HEX TENSION SCREW (55) into each of the two GUIDE RODRETAINERS (15). Do not
fully thread the M10 x 50mm HEX TENSION SCREWS (55) into the GUIDE ROD RETAINERS (15).
Slide the GUIDE RODRETAINERS (15) into the holes on the RIGHT TOWER (11). Make sure the M10 x 50mm
HEX TENSION SCREWS (55) in the GUIDE ROD RETAINERS(15) are facing up.
Push the GUIDE RODRETAINERS (15) up high enough so that the GUIDE RODS (16) can be placed under
them.
Lower the GUIDE RODRETAINERS (15) over the GUIDE RODS (16).
Slide the RETAINERRINGS (54) up. Use a RETAININGRING PLIERto secure the RETAINER RINGS (54) into
the groove on the GUIDE ROD RETAINERS (15). If the groove is hidden inside the hole on the tube, use a 5mm
ALLEN WRENCH to loosen the M10 x 50mm HEX TENSION SCREW (55)until the groove is accessible.
Repeat this step to complete the LEFT TOWERassembly.
NOTE:The Side Shroud is not shown in
this illustration for clarity.