D-4

 

GROUND TEST PROCEDURE

 

D-4

 

 

 

 

 

WARNING

WARNING ELECTRIC SHOCK can kill

WARNING: This procedure is only suitable for applica- tions using DC mega testers up to 500V.

Note: This procedure is for ‘machines as built’ many modifications could have taken place over the life of a particular machine, so details of this procedure may need to be ‘adjusted’ to suit these modifications.

For prompt service contact your local authorised Liquid Arc Field Service shop.

The insulation resistance values listed below are from Australian Standard AS1966.1.

Disconnect input power by removing plug from mains supply.

Remove welding leads (gun and work lead) from the machine before any tests are carried out.

Remove plug from PCB, install a shorting socket into the harness plug. (The shorting socket is to have pins 4 & 5 jumpered together and all other pins jumpered together separately and insulated.)

Connect a shorting jumper across the connections to the capacitor and from the capacitor to each rectifier heat sink plate.

Set power switch to ‘on’ position.

Input circuit test: Connect one lead of the mega tester to the frame of the machine and the other lead to both the ‘active’ & ‘neutral’ terminals of the 240V input plug. Apply the test. (Minimum resistance 1M•)

Welding circuit test: Connect one lead of the mega tester to the frame of the machine and the other lead to the positive output stud. Apply the test. (Minimum resistance 1M•)

Auxiliary circuit test: Connect one lead of the mega tester to the frame of the machine and the other lead to jumper on pins 4 & 5 in the shorting socket. Apply the test. (Minimum resistance 1M•)

Input circuit to welding circuit test: Connect one lead- of the mega tester to both the ‘active’ & ‘neutral’ ter- minals of the 240V input plug and the other to the positive output stud. Apply the test(s). (Minimum resistance 10M•)

Input circuit to auxiliary circuit test: Connect one lead- of the mega tester to both the ‘active’ & ‘neutral’ ter- minals of the 240V input plug and the other to the jumper on pins 4 & 5 in the shorting socket. Apply the test. (Minimum resistance 1M•)

Welding circuit to auxiliary circuit test: Connect one- lead of the mega tester to the positive output stud and the other to the jumper on pins 4 & 5 in the shorting socket. Apply the test. (Minimum resistance 1M•)

Wire drive test: Connect one lead of the mega tester- to the positive output stud and the other to the drive roll shaft. Apply the test. (Minimum resistance 1M•)

Remove all harness shorting plugs and connect all plug and leads to PCB. Remove all shorting jumpers. If any problems are encountered, refer to your near- est authorised Liquid Arc Field Service Shop.

Handymig 170i

Page 37
Image 37
Lincoln Electric 170I manual Ground Test Procedure