9 Service

SL-PS Installation & Operation Manual

￿WARNING

De-energize and lock the solar control and pump to prevent them from accidentally being switched back on again by mistake before any maintenance or repair work.

Serviceisnotpermitteduntilcomponents and solar liquid have cooled.

Draining the system

Fit corresponding drainage hoses on to the filling and

 

flushing connections and guide these into a collecting

 

vessel.

Open the check valves by placing the red and blue

 

thermometer handles in their 45° position.

Air separator

The solar station features an air separator. Open bleeder valve until the solar liquid exits free of air bubbles.

Check system pressure and top off solar liquid if required.

Flat seal screw connections

The screw connections may have to be retightened as the seals settle. Note tightening torque requirements in the “Technology: installation and commissioning” section of this manual.

Clamp ring screw connections

Use an open-ended wrench to retighten clamp ring screw connections if required (approx. 33 Ft lb).

When tightening the clamp ring screw connection, use two wrenchesone wrench to prevent the pumping station from turning.

Disassembling the solar station

(Wall bracket, for repairs and service only)

Use a screwdriver or similar tool to remove the retaining springs to the front.

￿ CAUTION

The solar station is now loose. Ensure

that it does not slide forward and out

 

of the wall bracket.

Open the fill/flush valve (return) under the pump.

Open the fill/flush vlave (forward flow) on the safety group.

Optional: Open the fill/flush valve at lowest point of

 

system, as close to the tank connection as possible.

Open bleeder equipment at highest point (above

 

collectors).

14