9 Service
WARNING
Serviceisnotpermitteduntilcomponents and solar liquid have cooled.
Draining the system
■ | Fit corresponding drainage hoses on to the filling and |
| flushing connections and guide these into a collecting |
| vessel. |
■ | Open the check valves by placing the red and blue |
| thermometer handles in their 45° position. |
Air separator
■The solar station features an air separator. Open bleeder valve until the solar liquid exits free of air bubbles.
■Check system pressure and top off solar liquid if required.
Flat seal screw connections
■The screw connections may have to be retightened as the seals settle. Note tightening torque requirements in the “Technology: installation and commissioning” section of this manual.
Clamp ring screw connections
■Use an
■When tightening the clamp ring screw connection, use two
Disassembling the solar station
(Wall bracket, for repairs and service only)
■Use a screwdriver or similar tool to remove the retaining springs to the front.
CAUTION | The solar station is now loose. Ensure |
that it does not slide forward and out | |
| of the wall bracket. |
■ Open the fill/flush valve (return) under the pump. | |
■ Open the fill/flush vlave (forward flow) on the safety group. | |
■ | Optional: Open the fill/flush valve at lowest point of |
| system, as close to the tank connection as possible. |
■ | Open bleeder equipment at highest point (above |
| collectors). |