Comet installation and user manual: E-6761200XT/FA 4.1Merlin Gerin by MGE UPS SYSTEMS
17
I
+–
!
!
O
2221
bip...bip...
put first the input power switch 1and then the battery circuit breaker 4in
"on" position:
the buzzer 17 sounds,
the green "load protected" light 21 goes on,
the rectifier 2and the charger 6start up,
the inverter 7automatically starts up, except if the system is in "manual
start-up" mode (optional). In this case, press the green "inverter on" button 22 .
start-up
Fig. 18
powering up to Comet Caution:
As soon as AC input power is supplied to Comet (upstream circuit breaker
on the low voltage switchboard in "on" position), the load is supplied via
the "static bypass" 3 . No indications are given on the control panel.
BY-PASS
NORMAL
TEST 2
TEST 1
"manual maintenance bypass"
switch

preliminary checks

check the settings of the protection devices:
input power switch 1in off (O) position,
battery circuit breaker 4in off (O) position,
"manual bypass" 8switch set to "NORMAL" position (see figure 18);
check that nothing can block the ventilation system (air entry through the
bottom and, where applicable, through the side vents);
check that there is a minimum 100mm clearance at the back for ventilation;
check that Comet no longer rests on its 4 wheels (lifting jacks in place);
check that the load-circuit circuit breakers (where applicable) are in off (O)
position.