Comet installation and user manual: E-6761200XT/FA 5.1
Merlin Gerin by MGE UPS SYSTEMS
press the "inverter off" button 23 for three seconds:
the green "load protected" light 21 goes off,
the red "load not protected" light 18 goes on,
the buzzer 17 sounds,
the inverter 7stops if the transfer conditions are correct,
the load is supplied directly by AC input power via the "static bypass" 3;
in the event of fault, see the Alarms section.

inverter shutdown

bip...bip...
21
I
+–
!
!
O
231817
powering down It is recommended not to power down Comet for long periods because the
battery should remained charged. However, to carry out a power down, proceed
as follows:
shutdown the inverter 7;
put the battery circuit breaker 4in "off" position;
turn off the input power switch 1;
all the indicating lights on the control panel go off.
Caution:
The load is still supplied by AC input power via the "static bypass" 3 ;
put the upstream circuit breaker(s) on the low voltage switchboard in "off"
position.
shutdown