TOW PREPARATION,TOTOW &TO LIFT
Preparation
1.Remove R.H. floor panel (4).
2.Install tow lever (from the toolbox) in pos. 1.
3.Turn tow lever clockwise to pos. 2.
4.Turn the steering wheel counterclockwise (left) until the resistance increases and the steering starts moving slightly.
5.Turn the tow lever to pos. 3.
Towing (see page “To tow”)
Reposition for drive
1.Turn tow lever back to pos. 1.
2.Remove tow lever.
3.Replace floor panel
Attention!
Diesel engine may only be started in pos. 1
Not included in all types.
Towing
Only tow the machine in case of emergency for the purpose of moving the machine out of the hazard area (maximum of
10meters). Towing eye (1a)
Transport machine with lifting brackets and transporter.
1 Articulation lock
Before attaching the machine affix articulation lock.
2Attachment to load hook Suspend machine on crane hook.
WARNING!
Never stand under lifted machine! While loading or unloading the machine, use only ramps. While transporting the machine, it must be secured against rolling, sliding and tipping over.
PAGE 24 — TANDEM ROLLER: T16 — PARTS & OPERATION MANUAL — REV. #2 (03/12/01)