Commissioning

6 Commissioning

This chapter describes the most common items that need to be checked before DNT2Mi-fp is taken into use.

DNT2Mi-fp is ready to operate after the power supply (AC/DC converter, DC or remote power) and port and line cables are connected. However, identifications and settings should be checked and, if required, statistics and error counter should be reset.

DNT2Mi-fp can be configured, tested and controlled via:

Service Terminal (using Q1)

Macro Service Terminal Emulator or Craft Terminal running on a PC (using Q1)

Other Nokia management products, such as Nokia NMS, can be used for the same purpose.

Menu structure for Q1 management is shown in chapter Factory Settings.

Note

It can take up to 60 seconds to save the altered settings. If the power is switched off during this time, the new settings will be lost. During the saving process, you can use the equipment normally.

Automatic power-up test

When the power is switched on, the unit performs an automatic self test, which is used to check the most vital operational functions of the equipment.

During the power-up test, the LEDs are lit in the following sequence:

1.All 3 LEDs are lit for 10 seconds.

2.The green power LED is blinking and other are off for 10 seconds during startup and self test.

3.The green power LED is lit and DNT2Mi-fp is ready for use.