Pella 80ED0101 Rough Opening Preparation, A. Verify the opening is plumb and level

Models: 80ED0101

1 8
Download 8 pages 20.35 Kb
Page 2
Image 2
1 ROUGH OPENING PREPARATION

YOU WILL NEED TO SUPPLY:

ss#EDAREOR )MPERVIOUSOSHIMSSPACERSMTO  ss GALVANIZED ROOlNGlNAILS  LB A. Verify the opening is plumb and level.

ssX CORROSIONIRESISTANT mAT HEAD WOOD SCREWS OR equivalent screws for concrete applications B. Verify the window will fit the opening.Manual backgroundManual backgroundManual backgroundManual backgroundManual backgroundManual backgroundManual backgroundManual backgroundManual backgroundManual backgroundManual backgroundManual background

ss#LOSED CELLEFOAM BACKERLRODSEALANT BACKERN TO CFT

ss0ELLA® SmartFlashfoil backed butyl window and door flashing tape or equivalent

ss(IGHGQUALITYUEXTERIOR GRADE POLYURETHANE ORNSILICONE

sealant (1 tube per window)

SEALANT

ss'REATA3TUFF Window and Door Insulating Foam Sealant by the Dow Chemical Company or equivalent low pressure polyurethane window and door foam

-DO NOT use high pressure or latex foams ss)NTERIORRTRIM ANDORRJAMB EXTENSIONSO TO MFT

INSTALLATION CLIP OPTION:

ss OR )NSTALLATIONLCLIP Manual backgroundManual backgroundManual backgroundManual backgroundManual backgroundManual backgroundManual background

ss X XCORROSIONIRESISTANT mAT HEAD WOOD SCREW Manual backgroundManual backgroundManual backgroundManual backgroundManual backgroundManual background ss X  CORROSIONIRESISTANT mAT HEAD OR  X

1-1/2" masonry screws for concrete block applications Manual backgroundManual backgroundManual backgroundManual backgroundManual backgroundManual backgroundManual backgroundManual backgroundManual backgroundManual background

TOOLS REQUIRED: ss4APEPMEASURE Manual background ss,EVEL Manual background ss3QUARE Manual background ss(AMMER Manual backgroundManual background ss3TAPLER Manual backgroundManual backgroundManual backgroundManual backgroundManual backgroundManual background ss3EALANT GUN Manual background ss3CISSORS ORSUTILITY KNIFE Manual background ss3TIFF PUTTY KNIFE Manual backgroundManual background ss0HILLIPSLSCREWDRIVER Manual backgroundManual backgroundManual backgroundManual background ss$RILL Manual backgroundManual backgroundManual backgroundManual backgroundManual backgroundManual backgroundManual background ss$RILL BITS  AND  Manual backgroundManual backgroundManual background

REMEMBER TO USE APPROPRIATE PERSONAL PROTECTIVE EQUIPMENT.

1 ROUGH OPENING PREPARATION

A. Verify the opening is plumb and level.

Interior

Note: It is critical that the bottom is level.

 

B. Verify the window will fit the opening.

1A

 

Measure all four sides of the opening to make sure it is 1/2" larger than the window in both width and height. On larger openings measure the width and height in several places to ensure the header or studs are not bowed.

Note: 1-1/2" or more of solid wood blocking is required around the perimeter of the opening. Fix any problems with the rough opening before proceeding.

Interior

1B

C.Cut the water resistive barrier (1C).

D.Fold the water resistive barrier (1D). Fold side flaps into the opening and staple to inside wall. Fold top flap up and temporarily fasten with flashing tape.

Water Resistive Barrier

Manual backgroundManual background1st cut

Manual background3rd cut

1C

2nd

cut

4th cut:

Make a 6" cut up from Manual background each top corner at a 45°

angle to allow the water resistive barrier to be lapped over the fin at the head of the window.

Exterior

1D

E.Apply sill flashing tape #1. Cut a piece of flashing tape 12" longer than the opening width. Apply at the bottom of the opening as shown (1E) so it overhangs 1" to the exterior.

Note: The tape is cut 12" longer than the width so that it will extend 6" up each side of the opening.

F.Tab the sill flashing tape and fold. Cut 1" wide tabs at each corner (1/2" from each side of corner) (1F). Fold tape to the exterior and press firmly to adhere it to the water resistive barrier.

1"

1E

6"

1/2"

1/2"

1F

Page 2
Image 2
Pella 80ED0101 installation instructions Rough Opening Preparation, A. Verify the opening is plumb and level