INSTALLATION
13.Verify that the brackets are seated firmly, then tighten the wing nuts on the rear
14.If installing additional EBMs, repeat Steps 7 through 13 for each cabinet.
15.Continue to the following section “EBM Installation.”
EBM Installation
C A U T I O N
A small amount of arcing may occur when connecting an EBM to the UPS. This is normal and will not harm personnel. Insert the EBM cable into the UPS battery connector quickly and firmly.
To install the EBM(s) for a UPS:
1.Verify that all battery circuit breakers are in the OFF (O) position (see Figure 9).
2.Plug the EBM cable(s) into the battery connector(s) as shown in Figure 9. Up to four EBMs may be connected to the UPS.
NOTE The batteries charge to 80% capacity in less than 5 hours. However, it is recommended that the batteries charge for 48 hours after installation or
20 | EATON Powerware® BladeUPS® EBM User's Guide S 164201650 Rev 2 www.powerware.com |