PP-FCMA-QL

Attaching the Pipe Clamps

1/4” KEP Nut

Pipe Clamp

PP-FCMA-QL

Step Bolt

Ceiling Tile

Step 1. Locate the pre-installed step bolts that are on the PP-FCMA-QL.

Step 2. Remove the four (4) black rubber caps from the step bolts.

Step 3. Lower the pipe clamp onto the step bolt.

Step 4. Secure the pipe clamp to the PP-FCMA-QL using a 1/4” KEP nut (see above).

Step 5. Tighten all hardware with a wrench (commercially available).

Step 6. Re-attach the four (4) black rubber caps onto the step bolts.

Step 7. Repeat steps 1 through 3 for the remaining pipe clamp installation.

Attaching the EMT Conduit Pipe (Optional)

M8 x 20mm Screw

and M8 Nut

 

Pipe

Ceiling

T-Bar

PP-FCMA-QL

Pipe Clamp

Step 1.

For added security, slide two (2) 3/4” EMT conduit pipe (commercially available) through the pipe clamps.

Step 2.

Once the EMT conduit pipe (commercially available) is installed, use a screwdriver to tighten the four (4) M8 x 20mm

 

Phillips head screws and four (4) M8 nuts.

 

 

 

The EMT conduit pipe must cross over two sections of the T-bar framework on both sides of the pipe clamps.

Installation Instructions

Page 7

Page 7
Image 7
Premier Mounts PP-FCMA-QL Attaching the Pipe Clamps, Attaching the EMT Conduit Pipe Optional, Step