Standby Generator Sets

Installation

START-UP CHECKLIST

Before working on the generator, ensure the fol- lowing:

The AUTO/OFF/MANUAL switch is in the OFF position.

The 120VAC supply to the battery charger is switched OFF.

‹PREPARATION FOR START-UP

Ensure that the 120VAC circuit breaker to the bat- tery charger is open.

Remove the fuse from the the control panel. Open the front door of the control box and remove the 15 Amp ATO fuse in the lower left-hand corner of the control box.

Connect the battery cables to the battery. Attach negative battery cable last.

Close the 120VAC circuit breaker to the battery charger.

Measure the voltage at the battery before and after the charger is turned on.

Verify all AC electrical connections are tight at the circuit breaker and transfer switch.

Visually inspect entire area looking for loose paper, plastic wrappings, leaves, etc.

Check all hoses clamps fittings for leaks or dam- age.

Check all electrical plugs throughout the genera- tor. Ensure each plug is seated correctly and fully inserted into its receptacle.

Verify the AUTO/OFF/MANUAL switch is in OFF position.

Open the valve to the engine fuel line.

Bleed the fuel system of air. (necessary for long fuel lines).

Open the generator main line circuit breaker.

Connect a manometer to the gas line and record the static pressure. It must be as listed in the Specifications.

Insert the fuse into the control panel.

Move the AUTO/OFF/MANUAL switch to the man- ual position. The engine should now crank and start.

Check voltage at the generator terminals.

For 3-phase units, check phase rotation at the transfer switch terminals. The generator phase rotation must match the utility phase rotation.

Check for coolant, fuel, oil, and exhaust leaks.

Close the generators main line circuit breaker.

Turn the generator set off.

Connect the UTILITY supply to the transfer switch.

Set the AUTO/OFF/MANUAL switch to AUTO.

Disconnect utility power before the transfer switch.

Engine should start, transfer to load.

Run at least 15 minutes on generator power. Make certain all 3-phase loads are functioning correctly (correct phase rotation).

Reconnect Utility power

Transfer switch will transfer back to Utility and engine will shut down within the given time parameters set up for the specific transfer switch and controller.

Install all covers, access plates and door panels.

Put the Owners Manual in a safe and accessible place.

Make certain the AUTO/OFF/MANUAL switch is in the AUTO position.

05/06 B .Rev Install002

8-2

Page 14
Image 14
Siemens SG020 owner manual START-UP Checklist, ‹ Preparation for START-UP

SG020 specifications

Siemens SG020 is a cutting-edge turbine designed for a variety of energy applications, particularly in the field of renewable energy generation and industrial processes. As one of the latest innovations from Siemens, this turbine is engineered for efficiency, reliability, and environmental sustainability.

One of the main features of the SG020 is its advanced aerodynamic design. This turbine is built with large rotor blades that optimize wind capture, allowing it to function effectively even in low-wind conditions. The blades are also constructed from lightweight composite materials, enhancing both performance and durability. This design maximizes energy output while minimizing wear and tear, thereby extending the operational lifespan of the turbine.

Incorporated within the Siemens SG020 is an intelligent control system that utilizes state-of-the-art sensors and software algorithms. This technology continuously monitors wind conditions and turbine performance, automatically adjusting the blade pitch and rotor speed to optimize energy production. The smart grid capabilities of the turbine allow it to integrate seamlessly with existing energy systems, making it a flexible solution for various applications, from powering remote communities to integrating with larger industrial facilities.

Another key characteristic of the SG020 is its commitment to sustainability. The turbine is designed to operate with minimal environmental impact, producing clean energy while reducing carbon emissions. Siemens has implemented eco-friendly manufacturing processes and materials in the production of the turbine, underlining the company’s dedication to environmentally responsible energy solutions.

Maintenance of the SG020 is also streamlined through innovative technology. Predictive maintenance features leverage data analytics to anticipate potential issues before they arise, allowing for timely interventions that further reduce downtime and maintenance costs. This enhances the overall reliability of the turbine, making it a dependable choice for energy generation.

The SG020 stands out as a flexible and efficient solution for delivering renewable energy. With its advanced technologies, robust design, and commitment to sustainability, it represents Siemens’ ongoing pursuit of innovation in the energy sector, paving the way for a more sustainable future in power generation.