Standby Generator Sets

Service Schedule

SERVICE SCHEDULE

The following is a recommended maintenance schedule for small standby and residential generator sets. The established intervals in the schedule are the maximum recommended when the unit is used in an average service application. They will need to be decreased (performed more frequently) if the unit is used in a severe applica- tion. Use calendar time or accumulated run time, from the previous maintenance interval to determine the next required maintenance interval.

Service Maintenance Interval Information:

The various service maintenance intervals are designated by interval numbers as follows:

1An early inspection of the generator set to insure it is ready to operate when required and to identify any poten- tial problem areas.

Performed monthly this requires approximately .5 man-hours per unit to complete.

This inspection may be performed by the end user providing the following safety steps are taken to prevent the engine from starting automatically without warning:

To prevent injury, perform the following steps in the order indicated before starting any maintenance:

Disable the generator set from starting and/or connecting to the load by setting the control panel AUTO/OFF/MANUAL switch to the OFF position.

Remove the 5 amp and 15 amp control panel fuses.

Turn off the battery charger (turn OFF utility supply to ATS).

Remove the negative battery cable.

The battery charger must be turned off BEFORE removing the battery cable to prevent an over current condition from burning out sensitive control panel components and circuits.

Following all maintenance, reverse these steps to insure the unit is returned to standby setup for normal operation when required.

2A break-in service inspection of the generator set to insure it is ready to operate and carry the load when required, and to identify any potential problem areas.

Performed ONLY ONCE following the first three months, or 30 run time hours of operation after purchase of the unit and requires approximately 2.5 man-hours per unit to complete.

This inspection contains some maintenance tasks which require special tools, equipment, and/or knowledge to accomplish and should be performed only by a Service Dealer.

3An operational inspection of the generator set to insure it is ready to operate and carry the load when required, and to identify any potential problem areas.

Performed semi-annually this requires approximately 1.5 man-hours per unit to complete.

This inspection contains some maintenance tasks which require special tools, equipment, and/or knowledge to accomplish and should be performed only by a Service Dealer.

4A mid-level inspection of the generator set to insure it is ready to operate and carry the load when required, and to identify any potential problem areas.

Performed annually this requires approximately 4.0 man-hours per unit to complete.

This inspection contains some maintenance tasks which require special tools, equipment, and/or knowledge to accomplish and should be performed only by a Service Dealer.

11-1

05/06 C .Rev SrvSchd002

Page 20
Image 20
Siemens SG020 owner manual Service Schedule, Service Maintenance Interval Information

SG020 specifications

Siemens SG020 is a cutting-edge turbine designed for a variety of energy applications, particularly in the field of renewable energy generation and industrial processes. As one of the latest innovations from Siemens, this turbine is engineered for efficiency, reliability, and environmental sustainability.

One of the main features of the SG020 is its advanced aerodynamic design. This turbine is built with large rotor blades that optimize wind capture, allowing it to function effectively even in low-wind conditions. The blades are also constructed from lightweight composite materials, enhancing both performance and durability. This design maximizes energy output while minimizing wear and tear, thereby extending the operational lifespan of the turbine.

Incorporated within the Siemens SG020 is an intelligent control system that utilizes state-of-the-art sensors and software algorithms. This technology continuously monitors wind conditions and turbine performance, automatically adjusting the blade pitch and rotor speed to optimize energy production. The smart grid capabilities of the turbine allow it to integrate seamlessly with existing energy systems, making it a flexible solution for various applications, from powering remote communities to integrating with larger industrial facilities.

Another key characteristic of the SG020 is its commitment to sustainability. The turbine is designed to operate with minimal environmental impact, producing clean energy while reducing carbon emissions. Siemens has implemented eco-friendly manufacturing processes and materials in the production of the turbine, underlining the company’s dedication to environmentally responsible energy solutions.

Maintenance of the SG020 is also streamlined through innovative technology. Predictive maintenance features leverage data analytics to anticipate potential issues before they arise, allowing for timely interventions that further reduce downtime and maintenance costs. This enhances the overall reliability of the turbine, making it a dependable choice for energy generation.

The SG020 stands out as a flexible and efficient solution for delivering renewable energy. With its advanced technologies, robust design, and commitment to sustainability, it represents Siemens’ ongoing pursuit of innovation in the energy sector, paving the way for a more sustainable future in power generation.