Pressurizing and starting up the unit:

After all pipes have been connected, pressurise the system gradually and check for leaks.

Turn the “Osmosis pump” switch to “I”. Check that the following message displays:

In normal operation the value Rj varies during osmosis-treated water production.

Wait 5-10 minutes, then continue by starting up the delivery pump.

Osmosis pump switch

I M P O R T A N T !!!

Delivery pump startup (first startup)

Remove the red bleeder cap P (“Sfiato innesco”) on the front (close to the pressure gauge, labelled as such) .

To remove the cap, press the John Guest clip and allow a bit of water to run into a container; refit the cap P, and actuate the “Delivery pump” switch.

FAILURE TO FOLLOW THIS PROCEDURE TO

THE LETTER CAN CAUSE SERIOUS

DAMAGE TO THE DELIVERY PUMP.

Delivery pump switch Cap “P”

- 35 -

Page 9
Image 9
Smeg WO-01 manual Pressurizing and starting up the unit, Delivery pump startup first startup