Periodic schedules case A
Start date | End date | Daily schedule | Transferred |
|
| index | at: |
07/01/2004 | 08/15/2004 | 051000001 | 06/30/2004 |
|
|
| 10:00:00 |
|
|
|
|
08/01/2004 | 08/02/2004 | 051000002 | 06/30/2004 |
|
|
| 11:00:00 |
|
|
|
|
Periodic schedules case B |
| ||
|
|
|
|
Start date | End date | Daily schedule | Transferred |
|
| index | at: |
08/01/2004 | 08/02/2004 | 051000002 | 06/30/2004 |
|
|
| 10:00:00 |
|
|
|
|
07/01/2004 | 07/15/2004 | 051000001 | 06/30/2004 |
|
|
| 11:00:00 |
|
|
|
|
Hint
To check the priority on an
After the Updating Information window is displayed, the list in the Content Management window shows the contents stored on the selected
Periods when no playout will be done on the
Note
The non playout periods have higher priority than any playout periods, regardless of the transferred order. You can specify them in advance.
Note however, that playout will not be done on these non playout days even if you send periodic schedules in which the same days are specified as the playout period.
1 In the
2 Select the Periodic Schedule tab of the Content Management window,
The Edit Periodic Schedule dialog box appears.
Operations Routine 4 Chapter
3 Select the No Playout option button, and specify the first and last days of the non playout period. Clicking the button of the
4 Place check marks for the days in the Day of the Week check boxes to specify specific days of the week in the period.
You can click each check box separately, or use the [Check All] or [Clear All] button.
To specify the Mondays in a period as non playout days, for example, click [Clear All], then click the Monday check box.
5 Click [OK].
A new periodic schedule for a non playout period has
Schedule Preparations | 51 |
|
|