6. Fill hole completely with concrete.
3
5
4
1" (2.54 cm)
IMPORTANT!: CONTINUE ON TO NEXT STEP.
DO NOT WAIT FOR CONCRETE TO CURE.
Tamp down concrete to release air pockets and build drainage hill. Level pole section in all directions several times while concrete is curing.
7.
1" (2.54 cm)
NOTE A:
Make a reference mark here for
NOTE B:
Keep flange pushed down to concrete and leveled.
1" (2.54 cm)
DRAINAGE HILL
PLAYINGSURFACE
SIDE
VIEW
IMPORTANT!: WAIT A MINIMUM OF 24 HOURS BEFORE GOING ON TO NEXT STEP.
CONCRETE MUST CURE.