3.8CLEANING & SANITIZING OF S0328 WITH
A.Empty freezer & mix container of product.
B.Mix 4 gallons of warm (120°F) detergent (Joy or equivalent) water and pour into mix container, brush mix container, pick up hose and draw tube. Pump detergent water into freezer hopper.
C.Mix sanitizer according to manufacturers instructions in quantities no less than 4 gallons. Pour sanitizer into mix container. Brush mix container, hose and draw tube to sanitize. Pump sanitizer into freezer hopper, empty remaining sanitizer from mix container and let air dry.
D.Drain detergent & sanitizer solution from the freezer.
E.Disassemble freezer according to Section 3, 3.3.
F.Clean freezer and parts according to Section 3, 3.4.
G.Sanitize freezer & parts according to Section 3, 3.5.
H.Assemble per Section 3, 3.6.
I.Sanitize per Section 3, 3.7.
3.9INITIAL FREEZE DOWN AND OPERATION This section covers the recommended operating procedures to be followed for the safe operation of the freezer.
A.Sanitize just prior to use.
B.Place the CLEAN/OFF/SERVE switch in the OFF position.
C.With the spigot open, pour one cup of mix into the hopper. Allow approximately 8 oz. of sanitizing solution and mix to drain out. Close the spigot and fill the hopper with mix.
D.Place the CLEAN/OFF/SERVE switch in the SERVE position. The product will be ready to serve in about 15 minutes.
3.10 REMOVING PRODUCT
Before disassembly, all product must be removed.
A.Open spigot and completely drain freezer.
B.Prepare not less than 3 gallons of warm detergent water and pour into hopper. (When using auto fill pump thru auto fill).
C.Use a brush to clean the hopper then completely drain freezer.
3.11SO328 OPERATION INFORMATION FOR SERVICE PERSONNEL
The SO328 is a cocktail/slush freezer. It is available in
1. Filling
To fill the freezer, pour mix into hopper until full. To fill freezers with the optional
2. Operation
Once the freezer is full of mix, turn the
3. Pump Operation
When the mix level in the hopper drops below the bottom level probe, the solenoid valve opens and the pump begins to fill until the top level probe is satisfied. When satisfied, the solenoid valve closes, and pump will continue to run until shut off pressure is reached. The electric pump will run until the pressure reaches the