ATP

4-1

4.0 ACCEPTANCE TEST PROCEDURE

4.1 Preliminary Information

This test procedure is intended to serve as the final proof of performance document
for the 7122B/7133B ACU, subsequent to field installation and set-up. Prior to the
performance of these tests, the system must have been installed and adjusted as
described in Section 2.0 of this manual. Motor rotation direction should be normalized
and limit stops should be set.

4.2.1 Maintenance Mode

1. On the 7122B/7133B OU set the MAIN POWER circuit
breaker to ON. _______(Check)
2. Verify that the EMERGENCY STOP button is in the out
position. _______(Check)
3. Set the MAINT/REMOTE switch to MAINT. _______(Check)
4. Using the EL UP/DOWN switch, drive the antenna and
verify correct directional movement of the antenna. _______(Check)
5. Using the EL UP/DOWN switch, drive the antenna UP
and verify that the limit switch stops the movement of
the antenna. _______(Check)
6. Using the EL UP/DOWN switch, drive the antenna DOWN
and verify that the limit switch stops the movement of the
antenna. _______(Check)
7. Using the AZ CW/CCW switch, drive the antenna and
verify correct directional movement of the antenna. _______(Check)
8. Using the AZ CW/CCW switch, drive the antenna CW
and verify that the limit switch stops the movement of
the antenna. _______(Check)
9. Using the AZ CW/CCW switch, drive the antenna CCW
and verify that the limit switch stops the movement of
the antenna. _______(Check)