12 | Vertical Tracks | |
Tools: Power Drill, 3/16” Drill bit, 7/16” Socket driver, Tape measure, | ||
Level, Step ladder | ||
|
IMPORTANT: If your door is to be installed prior to a finishing construction of the building’s floor, the vertical tracks and the door bottom section assembly should be installed such that when the floor is constructed, no door or track parts are trapped in the floor construction.
Important: The tops of the vertical tracks must be level from side to side. If the bottom section was shimmed to level it, the vertical track on the shimmed side must be raised the height of the shim.
Position the left hand vertical track assembly over the track rollers of the bottom section. Make sure the counterbalance lift cable is located between the track rollers and the door jamb. Drill 3/16” pilot holes into the door jamb for the lag screws.
Loosely fasten jamb brackets and flag angle to the jamb using 5/16” x
Note: Larger doors will use long stem track rollers with double graduated end hinges.
With assistance, lift second section and guide the track rollers into the vertical tracks. Lower section until it is seated against bottom section. Flip hinges up. Fasten center hinge(s) first; then end hinges last using
Repeat same process for other sections, except top section.
Important: Push & hold the hinge leafs securely against the sections while securing with
Note: Install lock at this time (sold separately). See optional installation step, Side Lock.
|
| Lock section |
|
| Vertical |
|
|
| tracks |
|
|
|
| ||
| Left | Intermediate | Right |
| end hinge | hinge(s) | end hinge |
14 | Top Section |
|
|
Tools: Hammer, Step ladder, Tape measure |
| ||
|
|
|
Place the top section in the opening. Temporarily secure the top section by driving a nail into the header near the center of the door and bending it over the top section. Now, flip up the graduated end and center hinge leaves, hold tight against section, and fasten center hinges first and end hinges last (refer to step, Stacking Sections). Vertical track alignment is critical. Position flag angle between
Flag angle
Vertical | 5/16” x |
track | |
assembly | Lag screws |
Jamb |
|
bracket |
|
12R FA 15R FA 12R QI 15R QI
Flag angle lag screw locations |
Important: the dimension between the flag angles must be door width plus
For Quick Install Track:
Complete the vertical track installation by securing the jamb bracket(s) and tightening the other lag screws. Repeat for other side.
For Fully Adjustable track:
Complete the vertical track installation by securing the jamb bracket(s) and tightening the other lag screws. Push the vertical track against the track rollers so that the track rollers are touching the deepest part of the curved side of the track; tighten all the track bolts and nuts. Repeat for other side.
Bottom | Track |
section | rollers |
3/8” to 5/8” |
| |
Spacing |
| |
Bottom section |
| |
Vertical track | Track roller | |
Floor | ||
|
Flag angle
Door width
+
Nail
Top section
13 | Stacking Sections | |
Tools: Power drill,7/16” Socket driver | ||
|
Note: Refer to door section identification, located in the
Note: The sections can be identified by the graduation of the factory installed graduated end hinges. The smallest graduated end hinge on section should be stacked on top of the bottom section, with each graduated end hinge increasing as the sections are stacked, see Parts Breakdown on page 2.
Note: Make sure end and center hinges are flipped down, when stacking another section on top.
Place track rollers into graduated end hinges of remaining sections.
Flag angle
Top section
Vertical track |
against rollers |
9
Please Do Not Return This Product To The Store. Contact your local
refer to your local yellow pages business listings or go to the Find a Dealer section online at