| (2) Front |
| (2) Rear |
| 3 Hole clips |
|
| (2) Sheave forks | |
cable lift sheaves | cable lift sheaves |
| (as required) |
| (as required) |
| (as required) | ||
|
|
|
|
|
|
|
|
|
|
(2) | Pushnuts | Counterbalance |
|
Eye bolts | (as required) | lift cables | Snubber cables |
Section height
Side view
Removing an Existing Door
3/8” - 16 x
(2)1/4” - 20 x 5/8” Tamper resistant screws
Stud Plate (as required)
5/16” x 1 5/8” Hex head lag screws (as required)
Important: Counterbalance spring tension must always be released before any attempt is made to start removing an existing door.
WARNING
A powerful spring releasing its energy suddenly can cause severe or fatal injury. To avoid injury, have a trained door systems tech- nician, using proper tools and instructions, release the spring tension.
1/4”- 20 Flanged | (2) | (2) 3/8”- 16 Hex nuts | (2) 1/4” - 20 Hex |
hex nuts (as required) | nuts (lift handles) |
(2) |
| |||
| Track bolts | Cotter ring | ||
nuts (as required) | Truss head bolts | (as required) | ||
| ||||
drilling screws (as required) | drilling screws (as required) | Carriage bolts (as required) |
1/4” - 20 x |
1/4” - 20 x |
Door Section Identification
Door Height | Bottom | Lock | Intermediate I | Intermediate II | Top | |
(Third) | (Fourth) | |||||
|
|
|
| |||
|
|
|
|
|
| |
6’0” | 18” | 18” | 18” | N/A | 18” | |
|
|
|
|
|
| |
6’3” | 21” | 18” | 18” | N/A | 18” | |
|
|
|
|
|
| |
6’6” | 21” | 18” | 18” | N/A | 21” | |
|
|
|
|
|
| |
6’9” | 21” | 21” | 21” | N/A | 18” | |
|
|
|
|
|
| |
7’0” | 21” | 21” | 21” | N/A | 21” | |
|
|
|
|
|
| |
7’6” | 18” | 18” | 18” | 18” | 18” | |
|
|
|
|
|
| |
7’9” | 21” | 18” | 18” | 18” | 18” | |
|
|
|
|
|
| |
8’0” | 21” | 18” | 18” | 18” | 21” | |
|
|
|
|
|
|
When installing your door you must use sections of the appropriate height in the right stacking order. What sections heights you need to use in what order depends on the height of your door.
Unless your door is five sections in height, you will not receive an Intermediate II section.
For detailed information see supplemental instructions “Removing an Existing Door/ Preparing the Opening”. These instructions are not supplied with the door, but are available at no charge from
Preparing the Opening
IMPORTANT: If you just removed your existing door or you are installing a new door, complete all steps in preparing the opening.
To ensure secure mounting of track brackets, side and center brackets, or steel angles to new or
The inside perimeter of your garage door opening should be framed with wood jamb and header material. The jambs and header must be securely fastened to sound framing members. It is recommended that 2” x 6” lumber be used. The jambs must be plumb and the header level. The jambs should extend a minimum of 12” (305 mm) above the top of the opening for Torsion counterbalance systems. For low headroom applications, the jambs should extend to the ceiling height. Minimum side clearance required, from the opening to the wall, is
Important: Closely inspect jambs, header and mounting surface. Any wood found not to be sound, must be replaced.
For Torsion counterbalance systems, a suitable mounting surface (2” x 6”) must be firmly at- tached to the wall, above the header at the center of the opening.
Note: Drill a 3/16” pilot hole in the mounting surface to avoid splitting the lumber. Do not attach the mounting surface with nails.
Weatherstrips (may not be included):
Depending on the size of your door, you may have to cut or trim the weatherstrips (if necessary) to properly fit into the header and jambs.
Note: If nailing product at 40°F or below,
Note: Do not permanently attach weatherstrips to the header and jambs at this time.
For Quick Install track: For the header, align the weatherstrip with the inside edge of the header and temporarily secure it to the header with equally spaced nails. Starting at either side of the jamb, fit the weatherstrip up tight against the temporarily attached weatherstrip in the header and flush with the inside edge of the jamb. Temporarily secure the weatherstrip with equally spaced nails. Repeat for other side. This will keep the bottom section from falling out of the opening during installation. Equally space nails approximately 12” to 18” apart.
For Fully Adjustable track: For the header, align the weatherstrip 1/8” to 1/4” inside the header edge, and temporarily secure it to the header with equally spaced nails. Starting at either side of the jamb, fit the weatherstrip up tight against the temporarily attached weatherstrip in the header and 1/8” to 1/4” inside the jamb edge. Temporarily secure the weatherstrip with equally spaced nails. Repeat for other side. This will keep the bottom section from falling out of the opening during installation. Equally space nails approximately 12” to 18” apart.
Headroom requirement: Headroom is defined as the space needed above the top of the door for tracks, springs, etc. to allow the door to open properly. If the door is to be motor operated,
Note: 6” low headroom conversion kit is available for 12” radius only. Contact your local
Backroom requirement: Backroom is defined as the distance needed from the opening back into the garage to allow the door to open fully.
4
Please Do Not Return This Product To The Store. Contact your local
refer to your local yellow pages business listings or go to the Find a Dealer section online at