Checking Supply Air CFM

174065-YIM-A-0206

Checking Supply Air CFM

To check the supply air CFM after the initial balancing has been completed:

1.Remove the two ¼ inch dot plugs in the duct panel.

2.Insert at least 8 inches of ¼ inch tubing into each of these holes for sufficient penetration into the airflow on both sides of the indoor coil.

3.Using an inclined manometer, determine the pressure drop across the dry evaporator coil. Since the moisture on an evapo- rator coil may vary greatly, measuring the pressure drop across a wet coil under field conditions would be inaccurate. To ensure

a dry coil, the compressors should be deactivated while the test is being run.

4.Knowing the pressure drop across a dry coil, the actual CFM through the unit can be determined from the curve in Coil Delta P vs. Supply Air CFM figure.

WARNING! Failure to properly adjust the total system air quan- tity can result in extensive system damage.

After readings have been obtained, remove the tubes and rein- stall the two ¼ inch plugs removed in Step 1.

NOTE: De-energize the compressors before taking any test measurements to ensure a dry indoor coil.

DEB Coil Delta P vs Airflow

 

0.4

DEB018

 

DEB024

 

 

 

 

DEB048

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

0.35

 

 

 

 

 

 

 

 

 

 

0.3

 

 

 

 

 

 

 

 

 

 

0.25

 

 

 

 

 

 

 

 

 

P

 

 

 

 

 

 

 

 

 

DEB018

 

 

 

 

 

 

 

 

 

DEB048

Delta

0.2

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

DEB024

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

DEB030, 36, & 42

Coil

 

 

 

 

 

 

 

 

 

0.15

 

 

 

 

 

 

 

 

DEB060

ID

 

 

 

 

 

 

 

 

 

 

 

0.1

 

 

 

 

 

 

 

 

 

 

0.05

 

 

 

 

 

 

 

 

DEB060

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

DEB030-42

 

0

 

 

 

 

 

 

 

 

 

 

400

600

800

1000

1200

1400

1600

1800

2000

2200

 

-0.05

 

 

 

 

 

 

 

 

 

Airflow (CFM)