Rheem RS80-42BP, RS47-21BP To Fill the Water Heater, See Key to Stub Out Details Below

Page 26

Installing the water heater.

NOTICE: This section does not apply if this system is installed as a pre- heater to an existing water heater.

!CAUTION: Do not connect the electricity to the main circuit breaker until the tank is full of water.

NOTICE: Ensure the plumbing is installed to allow for the removal of the storage tank end cover for the maintenance procedures.

See Key to Stub - Out Details Below:

All plumbing and wiring Stub-Outs to be a minimum of 18" above roof frame.

(E)Electrical service (240V, 20-amp required only if using auxiliary electrical backup in tank)

(R) 3/4" Relief Line

(H) Hot Supply to House

(C)3/4" Cold Supply to Rheem thermosiphon tank

NOTICE: Mixing valves should be installed to reduce the point of use water temperature by mixing hot and cold water in branch water lines. Contact a licensed installer or the local plumbing authority for further information.

Install hot and a cold water shut-off valves next to the existing water heater in a convenient location.

Electrical Installation

1.See “Connect the Storage Tank to the Electrical Supply Section” on page 29 for electrical requirements.

2.Install according to Figures on page 15, electrical schematic, and optional electrical connections.

Install Roof - Jack Panel

1.Remove the necessary roofing material,

2.Place the panel over the plumbing and electrical stub-outs and install it with nails or screws,

3.Flash and seal all roof penetrations.

4.Replace the roofing material.

Connect the Plumbing to the Storage Tank, (see the Figure at the top of page 25.)

1.Connect the cold water supply line to the storage tank.

2.Connect the solar hot water line to the Tee Adapter.

3.Connect the drain line to T/P Valve.

To Fill the Water Heater

!CAUTION: On new construction, Do Not fill storage tank and/or charge the closed loop system until the water heater is ready for use. Cover the collectors until the system is filled and charged. Place a tag on the system if it s not filled and charged.

Make certain the drain valve is completely closed.

Open the shut-off valve in the cold water supply line.

Open each hot water faucet slowly to allow the air to vent from the water heater and piping.

As the water heater fills, air will be pushed from the open outlet faucet. A steady flow of water from the hot water

faucet(s) indicates a full water heater.

Check the tank and cold water lines for leaks and repair any found.

Ensure that the storage tank is completely free of air by opening the T/P Valve until it discharges a steady stream of water.

Then close the valve.

The system is now ready to Test and Fill the closed loop as described in the next section of this manual.

26

Image 26
Contents Passive Solar Water Heating Systems Care and Cleaning Safety InformationInstallation Instructions Troubleshooting TipsIntroduction Keep the use of the Backup Heater to a Minimum Try to use Hot Water during Daylight HoursWater Temperature Setting Time/Temperature Relationship in ScaldsRead and Follow this Safety Information Carefully Installing the water heater System Parts ID List Storage TankSite Inspection Equipment Pre-InstallationRecord extreme weather conditions on checklist Review Local CodesArea Requirements for Collectors System Placement RequirementsNumber Installation Plumbing/Electrical stub-outCompass Pitch Mount No. of Collectors Roof InstallationsPitch Requirements Roof Support Requirements Roof Type Installation Type Supporting StructuresRoof Survey Conventional Roof ModificationsConventional Roof Modifications Truss Frame Modifications Branch Circuit Sizing and Wire Size Guide Customer ApprovalElectrical Schematic Electrical System RequirementsTypical Installation Type of Installation= Mixing Valve = Temperature & Pressure Relief Metal / Sturdy Tile Installation Plumbing System Schematic for Installation as Pre HeaterTypes of Roof Installation Supporting Structure installation Roof PreparationInstalling the water heater Page Pipe Leg Connection Detail Frame AssemblyLower Pipe Leg Installation Collector Installation Collector Fitting Installation DetailStorage Tank Installation Metal / Sturdy-TileExternal Piping Insulation Plumbing InstallationStorage Tank Plumbing Attachment Detail, Left Side To Fill the Water Heater Electrical InstallationInstall Roof Jack Panel See Key to Stub Out Details BelowTest and Fill Procedure Test and Fill the Closed LoopInstalling the water heater Neutral Connect Storage Tank to Electrical SupplyDetail of Electrical Connections Safety Controls Operating the water heater. Installation ChecklistSafety Precautions To replace the temperature limiting controlIf adjustment is necessary… Water Temperature SettingTime/Temperature Relationship in Scalds Draining the Water Heater Care and cleaning of the water heaterRoutine Preventative Maintenance Anode RodVacation and Extended Shut-Down Vacations or Brief AbsencesBefore You Call For Service… Problem Possible Causes What To DoLow Hot Water ‘A’ Frame kit consists Installations using 17.5 a FramesFrames Side Pitch Installations Tile Roof Against Pitch Installations Tiled Roof Variations for Metal and Fibreboard RoofsVariations for Shallow Pitch or Flat Deck Roofs Flashing and Roof PenetrationsIf YOU Need Service